Overchargi­ng probe at two power firms

- AUGUST GRAHAM

0fgem is probing two companies to find out if they overcharge­d the grid to lower their production levels.

The energy regulator said it was looking into whether EP SHB, which owns the South Humber Bank gas power plant, and SSE Generation broke the terms of their licences in a way that could have ultimately pushed up household energy bills.

A key part of ensuring that the lights stay on across Britain is to balance the grid.

This means it is important that power plants do not generate more electricit­y than households and businesses use at any given point, and vice versa. To do this the grid can ask electricit­y generators to stop producing, or reduce the amount of electricit­y they are putting into the grid.

In return the grid will often pay these producers to turn off or reduce their production.

But Ofgem is now looking into whether SSE Generation at times requested too much money to stop or slow production from its Foyers pumped storage power station.

The site works by pumping water from Loch Ness to Loch Mhor when electricit­y is in good supply.

It then allows gravity to push the water back down to Loch Ness, pushing it through a generator on the way to create electricit­y.

To slow production SSE Generation charged the

grid prices of up to £60 per megawatt hour (MWh) starting in May 2020.

This was “significan­tly more expensive” than the prices it had submitted in the past, Ofgem said.

The regulator will probe whether this breaks the duty of generators not to charge “excessivel­y expensive” prices.

Meanwhile, between

October 2019 and May 2021 EP SHB regularly set bid prices to reduce production at its gas plant at “a level which was particular­ly expensive for a gas-fired power station”, Ofgem said.

Reducing gas production also means that producers save money that they would otherwise spend on buying gas to burn.

EP SHB said: “As this is an open investigat­ion we have no comment to make at this stage.”

SSE said: “SSE notes Ofgem’s announceme­nt this morning in relation to its Foyers pumped storage power station. As a responsibl­e operator of generating assets, SSE will be complying fully with the investigat­ion.”

 ?? ?? LOCH NESS SITE: SSE Generation’s Foyers plant is at centre of an investigat­ion.