The Courier & Advertiser (Fife Edition)

Seagreen cabling complete

- GAVIN HARPER

Scotland’s largest offshore wind farm, off the Angus coast, has passed a significan­t milestone. The installati­on of more than 11 miles of onshore cabling has been completed for the Seagreen wind farm.

The cables are for three power circuits which run from landfall at Carnoustie to the project’s new substation, which is under constructi­on at Tealing.

The completion of the work comes despite the company behind the installati­on of the work, Roadbridge, being placed into receiversh­ip.

Nexan, principal contractor­s for the cabling, appointed firms to complete the final cable installati­on.

Work is ongoing to “progress the reinstatem­ent of the land”, a spokespers­on for the wind farm project said.

The completion of the cabling was hailed as a “massive feat of engineerin­g” by Seagreen’s onshore project manager Steven Reid.

It has included 117 cables installed along the route and has involved crossing the East Coast Main Line, the A90 and the A92.

Mr Reid added: “This was a key activity of the Seagreen project to prepare for the export of first power this summer.

“We are now in the final phase of work of reinstatem­ent and replanting of the land affected by the cable route which will continue to the end of the year.”

Mr Reid thanked local residents for their patience and understand­ing while work was undertaken.

A number of the cable drums will be donated to local schools.

Landfall works at Carnoustie were completed earlier this year.

Since then, the project has also successful­ly completed the second of three cable pulls to support the connection of the offshore and onshore cables.

Seagreen, scheduled to enter operation next year, is a £3 billion joint venture project between SSE Renewables and TotalEnerg­ies.

The first of 114 turbines at Seagreen, 17 miles off the Angus coast, was installed late last year.

The facility – the world’s deepest fixed bottom offshore wind farm – will manage 1,075MW of power generated by the wind turbines, providing clean power for around twothirds of all Scottish homes.

 ?? ?? PROGRESS: Installati­on of onshore cabling is a significan­t milestone in the £3bn project.
PROGRESS: Installati­on of onshore cabling is a significan­t milestone in the £3bn project.

Newspapers in English

Newspapers from United Kingdom