Relief as A90 flyover work is completed

- JAMIE BUCHAN

Abusy A90 flyover has finally reopened, more than a year after it was struck by a lorr y hauling a crane.

The bridge at St Madoes, between Dundee and Perth, was left extensivel­y damaged after the accident on Halloween night, 2019.

Its unceremoni­ous reopening on Saturday afternoon ends prolonged traffic misery for commuters and extra hardship for local businesses. Although the 13-month closure did not affect traffic on the A90, the bridge is the only direct link between the communitie­s of Glencarse and St Madoes.

The £650,000 repairs programme got under way earlier this summer, and was due to conclude last month.

But the project was hit by further delays when engineers uncovered more extensive damage.

A four-way traffic light system is now in operation at the bridge, with some minor Scottish Water work still to be carried out.

Conservati­ve councillor Angus Forbes said it was a relief for locals.

“The closure has caused considerab­le inconvenie­nce to my constituen­ts, who have been forced to take long diversions to get to and from work, not to mention the economic damage to the businesses in Glencarse who rely on customers from St Madoes,” he added.

“I believe that this should have been completed much

sooner, but I appreciate the communicat­ion from Bear Scotland over progress.

“I am just delighted to see it finally open and resurfaced.”

Mr Forbes said the traffic lights will remain in place for about two weeks.

“Scottish Water still need to finalise some repairs on a water main that the

bridge carries, but hope fully that can be completed very soon,” he said.

The completion of the project has cleared the way for improvemen­ts at St Madoes, including a new crossing on Main Road.

“This has been on the cards for some time and should have been

completed by now, but traffic lights which were in place to deal with the bridge closure meant that work was delayed,” said Mr Forbes.

Work, which will also involve the installati­on of a new bus shelter, is expected to begin on Mo n d a y November 30 and last for about three weeks.

 ??  ?? JOB DONE: The repaired bridge reopened on Saturday. Picture by Dougie Nicolson.