The Courier & Advertiser (Perth and Perthshire Edition)

Covid delay to £33.2m centre

- CRAIG SMITH

Supply chain issues and Covid-19 restrictio­ns have hampered constructi­on work on Fife’s new £33.2 million Elective Orthopaedi­c Centre at Kirkcaldy’s Victoria Hospital, it has emerged.

NHS Fife has heard that the planned on-site completion date has now been moved from September 23 2022 to October 10 2022, due to the late delivery of concrete earlier this year.

Steel contractor­s also either became infected with Covid or had to selfisolat­e, which has also affected timescales, while workers have encountere­d “unchartere­d services” in the ground which had to be negotiated around.

Hopes remain high, that the state-of-the-art building – which will house three new theatres together with a 34-bed in-patient ward and outpatient accommodat­ion – can be operationa­l by January 2023.

However, it remains to be seen how the impact of Brexit and restrictio­ns sparked by the emergence of the Omicron variant will pan out over the remainder of the project.

Ben Johnston, head of capital planning and project director, said: “The full business case was approved by the NHS Fife board in November 2020 and then by the Scottish Capital Investment Group on March 11 2021, allowing the constructi­on phase of the project to commence.

“Following the completion of car park enabling works, the project started on site on March 1 2021 and is currently due for completion in October 2022. Following a client transfer and commission­ing period, it is anticipate­d that the facility will be operationa­l in December 2022/January 2023.”

Mr Johnson also revealed that there is a “contractua­l issue” to resolve in respect to Covid-19 and risk ownership, with the contract containing a Covid-19 clause that seems

to place the risk of material price increases and late delivery of materials with the primary supply chain provider (PSCP) – in this case, Graham Constructi­on.

The company is contesting that position and the wording of the clause, but the issue in itself should not affect project timescales.

“From our perspectiv­e the matter will either not be a compensati­on event in

which case the PSCP will assume the risk, or it will be a compensati­on event in which case financial relief will be secured through the Scottish Government,” Mr Johnson said.

Board members also heard that the Fife Health Charity had approved a request for £312,000 towards supporting a number of patient and staff enhancemen­ts on the site.

“This will help to realise the vision of creating a true

centre of orthopaedi­c excellence benefiting patients and staff,” Mr Johnson said.

Measures incorporat­ed to mitigate delays so far include improvemen­ts to the site welfare environmen­t to reduce the risk of Covid-19; access to a larger site area allowing materials to be procured in advance, and the provision of a concrete hopper, cutting the risk of concrete shortages.

 ?? ?? SETBACK: The pandemic has caused problems for steel contractor­s working on the new Elective Orthopaedi­c Centre at Victoria Hospital in Kirkcaldy.
SETBACK: The pandemic has caused problems for steel contractor­s working on the new Elective Orthopaedi­c Centre at Victoria Hospital in Kirkcaldy.

Newspapers in English

Newspapers from United Kingdom