MCC Masterplan
Cost to MCC by 2027: £89 million
Areas completed by 2027: New Compton and Edrich stands, new East Gate Building, new Nursery Ground Increase in capacity: 2,000 Financial reserves at end of 2027: £33 million
Final completion date: 2032 Arguments against: Finance is based upon the ground hosting two test matches a year, which is not guaranteed