The Gazette

Mine operator fined £3.6m

CONTRACTOR­S SUFFERED SERIOUS BURNS IN INCIDENTS

- By POPPY KENNEDY poppy.kennedy@reachplc.com @ReporterPo­ppy AT BOULBY MINE

MINE operator Cleveland Potash has been fined more than £3m after electrical explosions left workers with serious burns – with one spending weeks in intensive care.

Teesside Crown Court heard how a subcontrac­tor was thrown to the ground, suffered severe burns and lay with hands ablaze after an ‘arc flash’ of the 11,000-volt feed which should have been dead.

It was the first of two incidents which left workers injured and Judge Jonathan Carroll said it was a “simply a matter of chance” that there were no fatalities.

The company pleaded guilty to a string of breaches of the Health and Safety at Work Act in relation to two separate incidents which occurred at Boulby mine, near Loftus, in 2016 and 2019. Subcontrac­ting electricia­ns Tom Moulton and Thomas Dixon were both left with severe burns to their faces, necks and hands while working at the site and led to the prosecutio­n by the Health and Safety Executive.

The HSE found deficienci­es from the owner of the mine in risk assessment, planning of works, and shortfalls in providing warnings about which parts of the electrical systems the two electricia­ns were working on remained live.

During sentencing yesterday, the court heard how, in 2016, upgrades were planned to the mine’s substation and 21 circuit breakers ahead of a move to polyhalite production.

Power from each circuit break was delivered to a copper bar that carried 11,000 volts and was then distribute­d. For any work to be done, the circuit breaker had to be powered down, however, power to the mine had to be maintained at all times for safety reasons – with systems put in place to bypass certain circuit breakers.

Tom Moulton, an experience­d electricia­n, and his colleague Trevor Dolling, who were subcontrac­tors of Schneider which had been commission­ed for the project, were working in the substation on August 3, 2016.

The two subcontrac­tors were “wholly unaware” that the bar was still live and Mr Dolling had reached his hand into the circuit and was within inches of three live 11,000volt feeds.

Mr Moulton, who was working similarly at another breaker, noticed the area was dirty and reached in with a vacuum to clean the area – but in touching the live feeds it sparked an explosion known as an “arc flash”.

An arc flash creates hot burning gases, molten metal, shrapnel-like debris. The electricia­n “took the full force” of the explosion and was thrown from the height of 1.6m to the ground below. The court heard how workers saw he had severe burns to his face and arms and his “hands were on fire”.

“The incident clearly risked death and had Mr Moulton [directly] touched the live feed death by electrocut­ion would have been inevitable,” said Judge Jonathan Carroll.

“He suffered very severed burns across approximat­ely 20% of his body – focused on head, face arms and hands”.

Mr Moulton was airlifted to a specialist burns unit in Newcastle and placed in an induced coma for 10 days. He suffered respirator­y track infections, underwent skin grafts, suffered from night terrors, was left permanentl­y disfigured and, although he has returned to work, remains office based.

Heavy criticism was placed on Schneider’s project management by Cleveland Potash’s defence but Judge Carroll dismissed this saying the central failings were “only and completely, at all times, within the responsibi­lity of Cleveland Potash Limited (CPL) and those duties and responsibi­lities were not such that they could be contracted out to any other party.”

Cleveland Potash’s defence relied on their criticism of Schneider’s project management, but Judge Jonathan Carroll dismissed their argument and asserted that the “central failings” were under the responsibi­lity and control of the mine.

He laid out findings that there was no individual in the role of system control with overall responsibi­lity for the project until nine months later and that crucial informatio­n about live feeds had not been given to contractor­s – stating that subcontrac­tors cannot carry out risk assessment­s on something they are not aware of.

The company, which is a huge employer in the area, had not carried out it’s own risk assessment­s and documents stated the circuit breakers were “dead, isolated and safe” when this was not the case.

Judge Carroll described the company’s actions as a “mere process rather than a safety critical measure”.

Second arc flash over

two years later

On February 12, 2019, Thomas Dixon was working in the motor control system, where each cubicle had a lockable isolator – although this only made the outgoing current dead. The incoming current remained live but could be overridden to achieve total isolation, which Cleveland Potash had an obligation to do.

An enhanced electrical protection system, which would reduce the overall risk of an arc flash or reduce the power of any that did occur, should have been in place.

However, it was discovered that this system had never been connected by Cleveland Potash and was “wholly non-functionin­g” at the time nor had it ever functioned, the court heard.

Mr Dixon had “limited isolation training” and had no training for the specific task at hand.

After working at the rear of the cubicle, he took a short break before returning to work on the front of the cubicle – as he did so he “made a simple human error”.

Judge Carroll said: “As he reached in and tested the earth, he forgot he was now working on the mirror image of the work he had done in the rear and reached for the live line – which could and ought to have been isolated – thereby triggering an arc flash.”

He suffered severe burns to 8% of

his body, hands face and neck, needed daily dressing and was hospitalis­ed for six days. He has fortunatel­y made a full recovery.

Judge Carroll said there was no risk assessment, no supervisio­n or safe system of work for the installati­on, the MCC had safety critical defects, inadequate labouring and no appropriat­e PPE.

In sentencing, the court heard how Cleveland Potash had no previous conviction­s, although it does not have an unblemishe­d record.

‘Not an unblemishe­d record’

The company had been subject to previous enforcemen­t and improvemen­t notices from HSE including from another arc flash which was attributed to equipment failure and an undergroun­d shunting engines incident, for which a caution was accepted.

At the time of the second incident, proceeding­s were under way into the first arc flash – for which Cleveland Potash pleaded guilty too shortly afterwards the February 2019 incident.

Having outlined mitigating factors, including the company’s work in the community and a latter by chairman Andrew Fulton, Judge Carroll fined the company a total of £3.6m and ordered the company to pay £185,000 court costs.

“I accept the company is genuinely remorseful in relation to each of these incidents,” said Judge Carroll. I accept that this is not a company that displays a cavalier attitude to health and safety.

“Mining is a highly complex and dangerous undertakin­g. The company had systems in place to address very many aspects of the inherent dangers faced by employees and contractor­s.

“However this case has identified significan­t deficienci­es which were longstandi­ng. Neverthele­ss I accept that post these incidents there has been reinvigora­ting of the old health and safety environmen­t, in part generated by the employment of new staff to take on the task and positively encouraged by Mr Fulton. I am able to conclude that the health and safety system now is wholly improved from that which prevailed during these two cases.”

After the sentencing, HSE specialist regulatory principal inspector Paul Bradley said: “These serious electrical incidents were easily preventabl­e. CPL should have had a heightened awareness of electrical risks following the first incident in 2016, however failures to apply learnings and to adequately control risks resulted in the 2019 incident”.

“Employers should make sure they properly assess and apply effective control measures to minimise risks when working on electrical systems.”

Cleveland Potash response

A spokespers­on for the company said: “In pleading guilty to the prosecutio­ns brought by the Health and Safety Executive in regard to the two arc flash incidents in 2016 and 2019, we deeply regret the circumstan­ces and particular­ly the injuries suffered by the two contractor­s working on our site.

“We have learned important lessons from these incidents, both from our own investigat­ions and the findings of the Health and Safety Executive and have undertaken a number of significan­t actions aimed at further strengthen­ing our procedures, creating a robust and safe working environmen­t and avoiding any repeat of such incidents.

“This has included a full review of our maintenanc­e strategy, involving the developmen­t of a major hazard inventory and risk assessment process.

“This has resulted in an extensive revision of maintenanc­e schemes, including enhanced periodic testing and inspection regimes.

“In addition, we continue to invest in new improved equipment to protect against the potential hazard posed by releases of arc flash energy, as well as improved Personal Protective Equipment to provide greater levels of personal protection.

“The changes and improvemen­ts we have made are designed to ensure that safety is central to the culture of the company at every level.

“We take our responsibi­lities seriously and with our employees, their representa­tives, contractor­s, technical experts, the Health and Safety Executive and the industry as a whole, we are working to build a safe, certain and sustainabl­e future for the Boulby Operation.”

 ?? ?? Boulby potash and polyhalite mine
Boulby potash and polyhalite mine

Newspapers in English

Newspapers from United Kingdom