The Herald

Subway work delays

Network unlikely to be running again by start of football season

- HELENMCARD­LE TRANSPORT CORRESPOND­ENT

THE Glasgow Subway is to remain closed for a further two weeks after renewal works hit “a number of issues”.

Strathclyd­e Partnershi­p for Transport (SPT), which operates the undergroun­d, said contractor­s had advised them of delays in completing the necessary tunnel upgrades.

There is now no official date for the Subway to re-open, but SPT said the works should be completed “about two weeks later than expected”.

The Subway has been completely closed to passengers since Saturday, July 2, but it was expected to re-open on Monday, August 1. The delay means it will now be closed for a total of six weeks.

Replacemen­t buses have been laid on instead, but passengers have complained that the service is unreliable.

SPT has not gone into detail over the cause of the delay, but heavy rain over the past few weeks has reportedly complicate­d the project by flooding some parts of the network, creating problems for engineers trying to lay concrete.

The works – which involve a full replacemen­t of the section in the tunnels known as “ramps and turnouts” – are being carried out as part of a £300 million modernisat­ion of the Victorian era transport system.

London-based Colas Rail was awarded more than £6m by SPT to complete the works, plus an additional “risk and contingenc­y” allowance and £500,000 a year for “call off” specialist support for the duration of the contract.

It is the biggest single engineerin­g aspect of the entire Subway modernisat­ion programme, and involves a complete overhaul of the trackbed and signalling systems for the turnout chambers – where the Inner and Outer Circles of the Subway overlap and where the trains exit and enter the network.

In a statement, SPT said: “The contractor working on the essential renewal works of Glasgow Subway has now advised SPT that it requires extra time to complete the works. Despite assurances, Colas Rail has now confirmed that due to a number of issues they will not be able to hand back the system at the agreed time.

“We are working with the contractor to identify a new return to service date which they have estimated to be about two weeks later than expected.”

The delays mean that the Subway is unlikely to be up and running in time for the new football season, which kicks off on Saturday, August 6, creating a potential headache for transport bosses who will have to find alternativ­e ways to shuttle fans to and from the Rangers stadium at Ibrox.

Eric Stewart, SPT assistant chief executive for operations, said: “This is the most significan­t engineerin­g aspect of the whole modernisat­ion programme which is being built to last for another 40 years. This is a regrettabl­e position and we are working with the contractor to pull back some of this lost time, as we endeavour to minimise any further disruption to our passengers.

“We apologise to all our passengers for this inconvenie­nce.”

The Subway modernisat­ion, which began in 2011, will see all 15 stations refurbishe­d and new driverless trains rolled out from 2020.

 ??  ?? UNDERGROUN­D: Has now been scheduled to re-open on August 1.
UNDERGROUN­D: Has now been scheduled to re-open on August 1.

Newspapers in English

Newspapers from United Kingdom