TIMELINE of saga
Friends of Oban Community Play Park’s timeline of events from August 2015. August 2015
Wicksteed on site to mark out drainage lines for Phase 1 of big play park. September 2015
The first turf lifted as drainage work starts. November 2015
The opening party is hosted by Atlantis Community Leisure (despite phase one of park not being open due to wet and mud). February 2016
Phase one of play park for five- to 15-yearolds was opened on February 12. March 2016
Swing seat removed from ‘old’ (under-fives) play park and access gate padlocked. May 2016
Council installs two bins and new self-closing gate to allow safe access to green field. September 2016
After a health and safety inspection, all play parks closed by council on 28th. October 2016
Meeting between Wicksteed, Bounceback and FoOCPP on October 6 regarding big play park flooring but no input from council.
Meeting on October 27 with council, Wicksteed and FoOCPP to agree short- and long-term actions over play park flooring.
Garden upgrade done by Wicksteed, installing a new path and border edging, chainsaw carvings, musical items, mirrors, memorial benches, new fencing and gate. November 2016
Temporary fixes done on flooring in big play park by Wicksteed. Council open garden and under-fives playpark on 8th and big play park on 22nd, but leave fence between garden and big play park. December 2016
Fence comes down on December 9. February 2017
French drain installed on the green field parallel to the metal fence by council. April 2017
Council part clear the under-fives play park on 5th and close the play park on 28th. June 2017
Under-fives, phase three opening party postponed due to delay in award of tender. July 2017
July 12 sees meeting to discuss maintenance, litter and the flooring in the big play park. Maintenance inspections have not been done regularly enough – zip wire is broken beyond repair.
July 17: Wicksteed on site to start phase three build. November 2017
November 29: Zip wire fixed by Wicksteed (two-and-a-half months after parts delivered, five months after issue highlighted). March 2018
Big play park closed on 16th due to problems with flooring. June 2018
Council apologises for issues and explains measures done to alleviate safety concerns prior to closure of park as a precaution. Decision is then taken to use local contractor to carry out remedial work in bid to have park up and running over the summer period. July 2018
Independent assessor on site to test big play park flooring. August 2018
Rocking seahorse in under-fives area is barriered off. Outstanding issue
No signage stating opening hours etc.