The Oban Times

Islands back on national grid after underwater cable fault

-

Electricit­y supplies for more than 3,000 residents across Jura, Islay and Colonsay are once again coming from the national grid four months after a fault developed on an electricit­y cable more than 260 feet underwater.

For islanders it meant facing winter weather reliant on local renewable projects and Islay's fossil fuel-dependent Bowmore Power Station, commission­ed in 1946.

Plans for an end-to-end replacemen­t cable running 5.1 miles between the Sound of Jura and neighbouri­ng Tayvallich on the mainland were drawn up.

Teams from Scottish and Southern Electricit­y Networks (SSEN) were involved but the project was not without its challenges.

An applicatio­n was lodged with the Scottish Government for a special licence to work across a heavily-protected area and the project was dependent on the right sea conditions for three days during winter.

Then came a trio of storms - Brendan, Ciara and Dennis and just as the weather settled, alarm bells over coronaviru­s started to sound.

But the multi-million project was completed last week, which will no doubt lead to sighs of relief from islanders and energy bosses.

The project was made possible with support from Easdalebas­ed Specialise­d Marine Support Ltd (SMS).

It provided four vessels to support the engineerin­g feat, including the ‘delicate' task of transporti­ng cable and the transfer of crew.

Core to SMS's involvemen­t was its 13.5m RIB called the Celtic Guardian. It was designed by Duncan MacGregor of Camarc, Dunoon; built by Edwin Payne of boat builders AluTech, Barcaldine, with electronic­s provided by Dave Simcox of Electrotec­h Marine Limited, Oban.

Official documents submitted to Marine Scotland show the formal applicatio­n also requested permission to use a 200-metre-long cast iron pipe weighing eight tonnes and 400 tonnes of rock filter bags to ‘stabilise' the cable.

Mark Rough, SSEN's director of customer operations, said: ‘We thank the community and local businesses for their patience and support as our teams worked on this essential cable replacemen­t project.

‘I'd like to thank everyone involved from our sub-sea teams, contract partners and renewable generators to colleagues working on the islands, Bowmore Power Station and our control room.'

Michael Russell, MSP for Argyll and Bute, added: ‘SSEN and its partners have done a tremendous job restoring the link despite appalling weather delaying the operation for a considerab­le time.

‘Their commitment to ensuring the islands are connected has been total even though it has involved laying a new cable at considerab­le cost.

‘They have also been good at keeping the communitie­s and elected representa­tives informed. I am sure everyone is grateful to them. Everyone hopes it will never happen again.'

 ??  ?? Work under way to fit the deep sea electricit­y cable linking Jura to the mainland
Work under way to fit the deep sea electricit­y cable linking Jura to the mainland

Newspapers in English

Newspapers from United Kingdom