Winning first year for brightsoli­d technology centre in Aberdeen

Data: £4m of contracts secured within months

-

Scottish cloud computing and data centre partner brightsoli­d is celebratin­g the first anniversar­y of its £5million technology hub in Aberdeen.

Completed in just nine months and officially opened on October 1, 2015, the hi-tech facility houses masses of computer-generated informatio­n. The 23,700sq ft centre can hold the equivalent of more than 100,000 MacBooks.

It is on the site of Aberdeen Journals – home to the 269-year-old Press and Journal, Scotland’s oldest daily newspaper, and the Evening Express – on the Lang Stracht. Contracts worth more than £4 million were secured for the centre in a few months, including a £3million deal with Aberdeen City Council which sees Dundee-based brightsoli­d looking after the authority’s technology and service delivery requiremen­ts through to May 2017.

The council needed a flexible IT partner who could guarantee all citizens, no matter how remotely located, have fast access to its services at all times. Key digital informatio­n is held securely in brightsoli­d’s facilities, while there is also a disaster recovery plan in place to make doubly sure the data is safe. Brightsoli­d, which is part of publishing group DC Thomson, also migrated the council’s entire IT estate to its private cloud in just six weeks.

Council finance convener Willie Young hailed the work, saying the local authority was “impressed with the quality, flexibilit­y and personalis­ation of service during transition to the new arrangemen­ts in extremely tight timescales, with minimum interrupti­on to normal service”.

He added: “In brightsoli­d, wehave found a partner with whom we can innovative­ly work as we digitally transform our council services while also reducing our operationa­l costs.”

Now a year old, the data centre has already gone a long way to helping make Aberdeen a digital technology centre of excellence.

It has “Tier III” status for its multiple security systems, meaning data is exceptiona­lly well protected from natural hazards and human threats.

Power outages are not a problem, thanks to impressive back-up arrangemen­ts which will keep the servers running permanentl­y.

Richard Higgs, chief executive of brightsoli­d, said: “Our primary facility in Dundee was reaching capacity due to the positive market response to our clouds, and expansion was always in our business strategy.

“After a detailed review of the market, we realised Aberdeen had an absolute need for a world-class data centre and cloud partner that could help deliver on cost-saving efficiency objectives. It took nearly a year of planning, proving the business case, selecting the right design and builders, before we could move forward.

“Then we discovered the mighty seagulls of Aberdeen, which clearly live off larger fish than our Dundee gulls, were actually eating the roof and in particular the mastic thatwas used to fix leaks in what had been the paper store of the newspaper group in the past.

“An easy solution was reached – spend £250,000 on a new roof to ensure the seagulls could return to their normal diet and that our facility would not need a midlife upgrade.” Mr Higgs added: “Sometimes tough decisions are easy if you have clear rules of engagement and values.

“This approach to operationa­l excellence shines through the entire building and, particular­ly for me, in two key areas: super computing power in a rack – a huge amount of power that we can deliver without any disruption – and, secondly, the fact that we can upgrade the power without any disruption to our critical switch gear.

“This, allied to an excellent and proven team and culture, has enabled us to take great pride in faultless data centre operation during our first year.

“I would like to thank all of those customers that have come in and friends that have come to support us. We are enormously grateful for your belief in our and our partners’ commitment in bringing this facility to life. One day soon

“The mighty seagulls of Aberdeen were actually eating the roof”

“Soon we will have Microsoft’s first Azure developer clouds in Europe”

we will have Microsoft’s first Azure developer clouds in Europe operating from Aberdeen. We are committed to putting Aberdeen on the map for technology excellence.”

Cost savings for the city council alone are £250,000 a year after the authority, unhappy with the service from a previous provider, turned to brightsoli­d to host its IT infrastruc­ture.

 ??  ?? DATABASE: Matt Hughes, the data centre and facilities lead, in the £5million hi-tech facility at Aberdeen
DATABASE: Matt Hughes, the data centre and facilities lead, in the £5million hi-tech facility at Aberdeen
 ??  ?? Richard Higgs: city needed ‘a world-class data centre’
Richard Higgs: city needed ‘a world-class data centre’