The Press and Journal (Inverness, Highlands, and Islands)

Opening date of bridge still uncertain after latest delay

Transport: Timeframe of mid-July to August given

- BY LYNSEY BEWS

The new Queensferr­y Crossing will notopenunt­il between mid-July and the end of August.

The latest delay has been caused by poor weather conditions, Scottish Economy SecretaryK­eithBrown said.

The £1.35billion bridge across the Forth was due to open last December, but adverse weather had already delayed the completion date to the end of May.

Mr Brown told Holyrood’s rural economy and connectivi­ty committee that contractor­s are “now advising that the opening to traffic date is more likely to be betweenmid-Julyand the end of August”.

He added: “To put that into context, that’s around a four to 10-week delay on a six-year constructi­on programme.

“The precise opening date will depend on the amount of weather downtime which occurs in the coming weeks, with the latest date being based on weather similar to that which we have seen in February and March.

“It is very important to stress that the costs associated with the overrun will be fully covered by the contractor and so will not result in any increase to the overall project cost to the taxpayer, which stands at £1.35billion as before.

“The potential overrun on the contractua­l completion date of between four and 10 weeks is a huge disappoint­ment to me and everybody involved with the project, but it should be kept in perspectiv­e in terms of infrastruc­ture projects of this scale and complexity.”

Mr Brown said there are now 1,500 people working on the bridge, with operations continuing around the clock.

Workers are being kept on standby to ensure no weather window is missed, he told MSPs.

Pressed on the newcomplet­ion date, Mr Brown stressed “weather is the master and that remains the case”.

There is a “very high degree of certainty” over the revised timeframe for the opening “but it is not absolutely certain”, he said.

Committee members were also told that although the winter had not been severe, wind speeds were a key issue.

Remaining activities are vulnerable to weather conditions, for example tower cranescano­nlyberemov­ed in wind speeds of less than 25mph and work on cable stays is also sensitive to wind.

David Climie, project director at Transport Scotland, said:“We have to plan the works very, very carefully, they are being planned literally on a dayto-day basis, and we have to rely on the weather forecastin­g informatio­n to plan the works properly.”

 ??  ?? SETBACK: Weather has disrupted work on the Queensferr­y Crossing, which was shrouded in coastal fog yesterday
SETBACK: Weather has disrupted work on the Queensferr­y Crossing, which was shrouded in coastal fog yesterday
 ??  ?? Keith Brown at the new Firth of Forth bridge
Keith Brown at the new Firth of Forth bridge

Newspapers in English

Newspapers from United Kingdom