The Press and Journal (Inverness, Highlands, and Islands)

School revamp £1m over budget

Cromarty primary revamp a third over budget and six months late

- BY JAMIE MCKENZIE

WORK to refurbish a Highland primary school has come in almost £1million over budget and half a year late – sparking fears for other school repairs in the north.

The final costs at Cromarty Primary School on the Black Isle were almost a third over the original £2.75million budget.

Politician­s and councillor­s believe the overspend could impact spending on other schools in desperate need of repairs.

MSP Kate Forbes said: “I’m cam- paigning to see schools in my constituen­cy upgraded.

“They could do a lot with £1million.”

An internal audit carried out by Highland Council blames the soaring cost on delays, partly caused by its own failure to carry out checks to prevent the collapse of a boundary wall during constructi­on.

“The discovery of a rare New Zealand flatworm also slowed down the works.

A major project to revamp a Highland school finished £1million over budget and nearly six months late – prompting fears there may not be enough cash for repairs elsewhere.

Cromarty Firth Primary School’s refurb and extension was nearly a third over the £2.75million budget due to major delays.

And an internal audit carried out by Highland Council has revealed the delays were partly due to the authority’s failure to carry out proper checks to prevent the collapse of a boundary wall during constructi­on.

“Morethanal­ittle bit frustratin­g that there’s less money in already lighter coffers”

An unforeseen and abnormal discovery of rare New Zealand flatworms on site during the project’s design state was also to blame.

Stuart Black, the local authority’s director of developmen­t and infrastruc­ture, admitted the work had been challengin­g but stressed the school now has a new extension which had been upgraded from a poor to an A-condition rating.

But fears are mounting among local politician­s and councillor­s that the overspend – coupled with budget cuts – will mean there is not enough cash for other Highland schools desperatel­y in need of repair.

Skye, Lochaber and Badenoch MSP Kate Forbes said: “This internal audit report makes for concerning reading, as it explains why the project to upgrade Cromarty Primary took so long and was a whopping £1million over budget. It begs the question why the problems with the boundary wall weren’t identified earlier on and the £1million could have been spent in other ways.

“I’m campaignin­g to see school buildings upgraded in my constituen­cy and, in particular, Invergarry, Broadford and Banavie Primaries as well as Fortrose Academy.

“They could do a lot with £1million and it’s more than a little bit frustratin­g that there’s less money in already lighter coffers.”

The council carried out an internal audit of the Cromarty school project after local members raised concerns. The final report will go before the audit and scrutiny committee today.

The project, initiated in 2012, was originally meant to cost £2.75million and last 47 weeks, but instead cost £3.75million and took 72 weeks - almost a third over budget.

Building was also put on hold in May 2013 due to problems securing additional land, but eventually got under way in early 2015 before finishing last May.

The review found that whole site surveys, risk assessment­s and pre-start investigat­ions were not fully performed as part of the project pre-planning process, meaning the condition and stability of the historic boundary wall was not fully assessed by the council or external consultant­s before work started. It says project costs “significan­tly exceeded” the approved budget due to unforeseen works, extra external works and additional profession­al fees and contractor­s on costs relating to the collapsed wall.

The author of the report concluded that concerns raised by local members have now been “validated.”

Black Isle councillor Craig Fraser, who lives in Cromarty, said: “I think that level of overspend is appalling and I am lost for words.

“There’s been a lot of upheaval with staff and pupils, and we find that months later there is a significan­t overspend. Where was the scrutiny and where were the checks and balances that should prevent such an overspend happening?

“What are the significan­t overspends coming in for other projects around the Highlands? A £1million overspend would go a long way to part funding a new school, or could be used in the schools estate repair program.”

Inverness West councillor Alec Graham said that, in his own ward, contractor­s working on the refurbishm­ent of Inverness High School found that more work was needed than first thought after they went on site in the summer.

Mr Graham, who sits on the environmen­t, developmen­t and infrastruc­ture committee, said: “The school estate (across the region) is not in the best condition but it could be significan­tly worse than the council thinks. Until you look completely at a building it’s not always apparent what it needs.

“The day-to-day revenue budget includes school repairs and that will certainly be under pressure. The capital programme is for new schools and major work and, similarly, there will be a lot of decisions about that.

“There is no question that the amount of work needing to be done greatly exceeds the amount of money available, so the result is you do the most pressing contracts first.”

 ??  ?? CONCERN: Local councillor Craig Fraser said the overspend on the school refurb and extension was ‘appalling’
CONCERN: Local councillor Craig Fraser said the overspend on the school refurb and extension was ‘appalling’

Newspapers in English

Newspapers from United Kingdom