The Scotsman

Ferry linkspan hailed as milestone for project

- By SCOTT REID

The installati­on of a link‑ span at Mcinroy’s Point, Gourock has been hailed as a significan­t milestone towards the completion of Western Ferries’ terminal investment.

The 30‑metre span, built by Ferguson Marine, was lowered into place via crane earlier this week. It is expected that the new facil‑ ity will be completed and fully operationa­l by mid‑ February after the terminal works were completed by George Leslie last month.

Western Ferries, which operates a passenger and vehicle ferry serv‑ ice between Gourock and Dunoon, said it has focused its investment programme on ensuring the “continued operationa­l resilience, flex‑ ibility and robustness that its customers rely on”.