The Scotsman

More misery for motorists as Crossing is delayed again

- By ALASTAIR DALTON

The Queensferr­y Crossing will now be completed more than two years late after transport chiefs admitted “snagging” works had been delayed again.

Evening lane closures are set to continue for almost another year.

Only two of 23 outstandin­g works have been completed. Two will not be finished until October next year.

Difficulti­es in getting resources for the finishing works have been blamed for the latest delays on the £1.35 billion bridge.

Drivers on the Queensferr­y Crossing face further disruption until next summer after ministers admitted work to finish the bridge had been delayed again.

Evening lane closures that should have ended last Sunday will now continue for almost a year.

Transport secretary Michael Matheson said the builders of the £1.35 billion bridge had experience­d difficulti­es getting resources for the work.

It will now be completed more than two years late.

The only remaining tasks should have been painting the underside of the road deck.

But an updated list showed only two of 23 of the works have been completed, with seven to continue into 2019 and two not now due to be completed until next October.

This is despite Mr Matheson telling MSPS in July the Forth Crossing Bridge Constructo­rs’ (FCBC) chairman had “given his assurance” all but the deck painting would be completed by last month.

Tasks that will not be finished until next year include work inside the deck and on gantries, external and internal painting, and cable maintenanc­e access cradles.

A spokesman for the Scottish Government’s Transport Scotland agency said: “Traffic management will come off in December, then return in spring to summer at night.”

Mr Matheson said: “Our contractor­s FCBC have indicated they have not made the progress with the snagging and finishing works as originally planned.

“The target date for completing this work was September 2018, but they have informed us they require further time.

“FCBC have said they have experience­d difficulty in mobilising the resources required to complete the outstandin­g works.

“But they are confident they will finish all but two areas of the remaining works by December 2018, with work on the remaining areas to commence in spring 2019.

“Where possible, traffic management will only be implemente­d during the night, as is standard.

“In response to feedback from road users about nighttime traffic management during the summer months, additional processes have been implemente­d to ensure that traffic volumes are reduced prior to traffic management being installed on the bridge.”

That follows The Scotsman highlighti­ng lanes were closed before traffic had eased.

Scottish Conservati­ve transport spokesman jamie greene said: “Commuters will conclude the SNP is playing catchup after hurrying to open the bridge triumphant­ly, at the expense of drivers.

Edinburgh Western Liberal Democrat MSP Alex Colehamilt­on said: “Residents and road users will be fearful this will mean closures and delays further down the road.”

 ?? PICTURE: LISA FERGUSON ?? 0 Disruption on the Queensferr­y Crossing should have ended last weekend
PICTURE: LISA FERGUSON 0 Disruption on the Queensferr­y Crossing should have ended last weekend

Newspapers in English

Newspapers from United Kingdom