Cost of new ‘game changer’ concert hall soars by £25m

- By BRIAN FERGUSON Arts Correspond­ent bferguson@scotsman.com

Edinburgh’s long-awaited new concert hall is set to cost at least £25 million more than expected.

Its main benefactor has suddenly upped its contributi­on to £35 million after it emerged the overall cost had soared to at least £70 million.

Earmarked for a site off St Andrew Square, the project has £25 million worth of support confirmed from the UK and Scottish government­s and the city council. A £10 million fundraisin­g campaign was launched two yeas ago.

The soaring cost is the second major blow to hit the project in weeks after it emerged that the developers of a nearby hotel and retail developmen­t have launched a legal challenge against the 1,000-seater venue, which will provide a home for the Scottish Chamber Orchestra and the Edinburgh Internatio­nal Festival.

The Dunard Trust, which has pledged to underwrite the project, has not publicly revealed the extent of its backing before now, although it was understood to be around £10 million due to the pledges of public funding on the table.

The Dunard Trust said it had “confidence” that the additional funding would allow Impact Scotland, the charitable trust pursuing the project, to “meet its goals.” However an official new cost for the first new concert hall to be built in Edinburgh for a century, will not be known until next year.

The Dunard Centre, which is to be named after the family trust overseen by American arts philanthro­pist Carol Grigor, received planning permission in April.

Impact Scotland confirmed that it was currently working with the contractor to “revise costs from early initial estimates.”

A spokeswoma­n for Impact Scotland said substantia­l work had to be down to keep the height and mass of the building down to ensure it could secure planning permission. The venue will also have a much deeper basement than originally anticipate­d.

A statement from Impact Scotland said: “We’re currently at the stage of working with our contractor to revise costs from early initial estimates.

“We have made considerab­le enhancemen­ts to the building during the design developmen­t stage, not least to address heritage concerns enabling us to be granted planning permission.

“The end result will be a better building – a game changer for music and performanc­e in Edinburgh.

“Revised costs will be available following the completion of the pre-constructi­on period next year.”

 ??  ??