The Scotsman

Late Ferguson Marine ferries delayed up to another five months

- By ALASTAIR DALTON adalton@scotsman.com

Further delays of up to five months to the completion of two long-awaited Calmac ferries have been announced by Ferguson Marine.

The latest setback was blamedonas­hortageofs­killed workers and Covid restrictio­ns at the Scottish Government-owned shipyard in Port Glasgow.

MV Glen Sannox, being built for the main Arran route between Ardrossan and Brodick, is now due to be finished between July and September next year compared to the previous estimate provided to MSPS last August of between April and June next year – three months behind.

Its unnamed sister ferry, codenamed hull 802, earmarked for the Skye-harrisnort­h Uist route, is now scheduled for completion between

April and July 2023, compared to between December 2022 and February 2023 – up to five months behind.

A spokespers­on for Ferguson Marine (Port Glasgow) said: “The Covid-19 pandemic caused six months of disruption in 2020 and productivi­ty has continued to be impacted due to a further shutdown in January 2021 and the introducti­on of additional safety measures.

"The timeline impact of ongoing disruption has been calculated as seven weeks, with additional costs of £1 million, which reflects the update given to Parliament in March this year.

"It brings the total Covid-19 costs to £4.3m, which is treated as an exceptiona­l item and does not affect the overall project budget.

"The overall project budget remains stable and unchanged at £110.3m.

“Recruitmen­t challenges since late 2020 have caused a delay of eight weeks as the shortage of local skilled labour meant that Ferguson’s had to meet resource requiremen­ts by subcontrac­ting smaller fabricatio­ns to Scottish businesses, which has supported 25 jobs, and introducin­g overseas workers.

“The report also outlines achievemen­ts and progress to date, including a major milestone in the build of MV Glen Sannox with the completion of structural work.

"Progress is visible with the installati­on of a reworked funnel and newly-constructe­d mast, as well as completion of the structure around the stern and inside the hull.

"Remedial work has been completed on hull paintwork and the first layers of protective paint have been applied.”

Newspapers in English

Newspapers from United Kingdom