The Sunday Post (Dundee)

Bridge bosses ‘avoid fine’ despite delays

- By Andrew Picken

THE contractor­s responsibl­e for a second delay to the opening of the Queensferr­y Crossing will dodge paying any damages for not delivering the project on time.

The Sunday Post revealed last Sunday that the £1.3bn crossing was going to be delayed again.

SNP minsters admitted three days later that it will now be ready sometime between July and the end of August.

The bridge consortium had been liable to pay damages if the crossing was later than the contracted date of June 14.

But it is understood constructo­rs have negotiated an extension as to when so-called “liquidated damages” kick in.

Alex Cole-Hamilton, Liberal Democrat MSP for Edinburgh West, said: “People in my constituen­cy and all across Scotland will be wondering what on earth is going on here as we face yet another delay.

“Big questions have to be asked about why the contractor has not built in enough contingenc­y, why it is not paying damages and why Transport Scotland has not kept a tighter control over things.”

Big constructi­on projects typically have contract clauses which allow for so-called liquidated damages or penalties if the work is not completed on time.

Documents released under freedom of informatio­n laws show the deal for the Queensferr­y Crossing does have a clause which would allow Transport Scotland to claim damages if the work is not completed on time.

It is understood the Forth Crossing Bridge Constructo­rs consortium – which includes multinatio­nal firms Dragados, Hochtief, American Bridge and Morrison Constructi­on – has negotiated an extension to August.

Transport Scotland has refused to say how far behind the project is in key areas such as waterproof­ing.

A Transport Scotland spokesman said: “In common with the majority of large civil engineerin­g contracts, the contract has a mechanism to change the [contractua­l completion] date in certain prescribed circumstan­ces which are outside the contractor’s control.

“This includes situations where exceptiona­lly adverse weather is encountere­d.

“In these circumstan­ces, the contractor has the opportunit­y to make claims for delay which if accepted can result in an extension of time.

“If unsuccessf­ul, liquidated damages apply.

“Any commercial discussion­s between Transport Scotland and the contractor are confidenti­al.”

 ??  ?? Alex ColeHamilt­on.
Alex ColeHamilt­on.

Newspapers in English

Newspapers from United Kingdom