Volunteers rise to the challenge to complete bridge build

The completed bridge at Harsfold.

-

THE last brick has been laid at the Wey & Arun Canal Trust’s latest restoratio­n project, a bridge at Harsfold in West Sussex.

Volunteers worked flat out to complete the bridge building project after floods, winter storms and then coronaviru­s lockdown put constructi­on behind schedule.

Small teams of six volunteers worked five days a week to get the job finished and allow the landowner access to his fields ahead of harvest.

Work on the 7m clear span steel and concrete bridge began in September but was set back by the deluge of rain and storms seen during December, January and February, making work ‘hard going’, according to project manager Dennis Gillen.

The compound, which is close to the River Arun, just escaped being flooded, but the mix of clay and rain meant the constructi­on site was a mudbath and delivery trucks and lorries struggled to reach the site. Just as the team managed to get the steel beams in, constructi­on was halted due to coronaviru­s lockdown.

When work resumed following easing of government restrictio­ns, volunteers had to operate in very different conditions and strict social distancing, but the team carried on undaunted.

Dennis paid tribute to the dedication of the volunteers: “They are an amazing team,” he said. “Everyone comes and gets on with it. They are all very skilled and great volunteers. They’ve worked so hard to get the job done.”

The area will now be reprofiled and the temporary bridleway diversion will be removed.

 ??  ??
 ??  ?? Some of the Harsfold team.
Some of the Harsfold team.
 ??  ?? Volunteers socially distancing while they work.
Volunteers socially distancing while they work.
 ?? PHOTOS: WACT ?? On the almost finished bridge.
PHOTOS: WACT On the almost finished bridge.

Newspapers in English

Newspapers from United Kingdom