West Lothian Courier

Station work running late after lift problem

- Sean O’Neil

Redevelopm­ent work at Livingston South station has been extended.

Work will now continue until February due to unforseen ground conditions and a delay in the design of the new lifts.

Following the completion of the first phase of the project to redevelop and extend the station platforms work was set to begin on creating the foundation­s for the new lift towers to improve accessibil­ity.

However, a geological investigat­ion of the area to be used for the lift foundation­s and for the new access staircase led to the need to redesign some elements of the proposed work, which had knock-on effects for other parts of the programme.

Bosses now say the redevelopm­ent of Livingston South station will be largely completed by December with the last element of work, commission­ing the lifts, scheduled for February 2019.

Brian Mallon, programme manager for the Shotts line electrific­ation programme, said: “We are conscious that the current situation at the station is not to the standard that we would want and expect for passengers using the railway.

“With that in mind, we are working with our contractor­s to expedite those elements of work that need to be progressed in order that we can fully complete the redevelopm­ent and deliver the station that the community of Livingston South expect.

“We apologise for any inconvenie­nce and pledge to do all we can to get the station completed as quickly as we can.”

No additional disruption to journeys through the station is anticipate­d as the project moves towards completion but station users may experience some changes to walking routes and other minor inconvenie­nce as outstandin­g work is completed.

The current situation at the station is not to the standard that we would want and expect Brian Mallon

Newspapers in English

Newspapers from United Kingdom