Western Daily Press

Costs of Bristol Beacon revamp spiral to £107m

- AMANDA CAMERON Local Democracy Reporter

THE anticipate­d cost of a major council project to refurbish the Bristol Beacon has more than doubled to an eye-watering £107 million.

Originally set at £48.8m in 2018, and revised to £52.2m a year later, the expected cost of the project has now spiralled to £106.9m, according to a new report.

Mayor Marvin Rees said the council had rejected the idea of abandoning or pausing the project.

The report, due before Bristol City Council’s ruling Labour group next week, also shows the former Colston Hall is not expected to be ready to hold its first show until the end of 2023.

It comes after workers unearthed a catalogue of unforeseen structural problems when they began gutting the building in 2019.

Elizabetha­n well shafts, Victorian stoves and hollow pillars propping up roofs were among the problems uncovered which “far outstrippe­d the worst-case scenarios contemplat­ed”, according to the new report.

Cabinet members are expected to approve the spending of an extra £58.1m, over and above the original budget of £48.8m, to complete the project when they meet next Tuesday.

Bristol taxpayers would foot the majority of the additional cost, with £44.5m coming from the council’s capital budget, according to the report.

It will mean less money is available for other capital projects the council may have embarked upon.

The remaining extra £13.6m is expected to be covered by £6.2m from the Arts Council, £6.3m from the West of England Combined Authority, and £1.1m which the Bristol Music Trust hopes to raise.

Scrutiny councillor­s privy to confidenti­al informatio­n about the project were shocked when the report was pulled from last month’s cabinet meeting at the last minute.

They accused the administra­tion of botching the tendering process and trying to hide the costs until after May’s local elections.

But officers blamed the delay in making the report public on its main contractor, saying Willmott Dixon’s “commercial behaviour” had prolonged live negotiatio­ns.

The council is still in “very challengin­g” negotiatio­ns with Willmott Dixon, according to the report, in an apparent attempt to transfer “95 per cent” of the financial risk.

It undertook a “thorough review” of the project in the wake of the newly discovered structural problems and developed a revised programme and costs with Willmott Dixon.

“This exhaustive process has resulted in a strong level of confidence in the revised project budget and duration required to complete the scheme,” according to the report.

“The initial budget was clearly inadequate once the structural and heritage items were discovered.

“We are now in a position to set an informed revised total capital investment budget of £106.9m.

“This is based on comprehens­ive informatio­n arising from the project review and includes appropriat­e project contingenc­y to manage project risk.”

“The completion date for the constructi­on contract is April 2023.

“The projected opening date for the new concert hall (allowing time for end user fit out and soft openings) is October 2023.”

The council will still be liable for additional costs that arise that have not been foreseen at the point of contractin­g.

The council said it had considered whether to mothball the refurbishm­ent project or abandon it entirely, but that both options would have cost the council significan­tly more than completing it.

“Funding already secured from funding bodies and other organisati­ons would have to be paid back, and the economic and cultural value of having a major cultural hub in the city centre would be lost,” a spokespers­on said.

Members of the council’s overview and scrutiny management board did not oppose the project’s completion when they discussed the matter, despite their shock at the new cost.

Bristol Mayor Marvin Rees said: “Bristol Beacon has been an iconic city centre venue for 150 years.

“Its unique cultural, economic and social value to Bristol means that pausing or abandoning the project would be an irretrieva­ble loss to the city, its arts and culture organisati­ons and citizens.

“We now know what secrets the building holds, and while this has meant a higher than expected cost to modernise and re-open the venue, our commitment to Bristol Beacon is so strong that investment remains the best financial and strategic option for the city.”

58 million pounds extra expected to be approved by Bristol City Council

 ??  ?? Ongoing work at Bristol Beacon; below, an image of how the building will look
Ongoing work at Bristol Beacon; below, an image of how the building will look
 ??  ??

Newspapers in English

Newspapers from United Kingdom