Western Mail

Transfer of key Valleys rail network is delayed

- RHODRI CLARK newsdesk@walesonlin­e.co.uk

THE planned transfer of a key part of the Valleys rail network to the Welsh Government has been delayed.

For the Core Valleys Lines (CVL) infrastruc­ture to transfer from Network Rail on September 20, as planned, Transport for Wales (TfW) would have had to “trigger” the process on July 25, but there are still unresolved issues.

TfW is currently unable to say when the process will be triggered and when the assets will be transferre­d.

But despite the delays, transport bosses remain confident they can still finish the promised upgrades, which will affect a huge swathe of the network, on time.

The government wants to take ownership of the lines north of Cardiff Queen Street, plus the Cardiff Bay branch and City Line, so that Transport for Wales and its contractor, Amey Keolis Infrastruc­ture, can modernise the tracks and trains in tandem.

There is a mountain of work ahead to electrify most of the 85 route miles, insert an additional track at 15 locations, build depots, bring in new trains and demonstrat­e that the

equipment is all safe for the public to use.

New tram-trains need to start carrying passengers on the Treherbert, Aberdare and Merthyr Tydfil lines by the end of 2022, to meet the deadline for EU funding. Tri-mode trains – using overhead power supply, batteries and diesel engines in different areas – are due on the Rhymney and Coryton lines by the end of 2023.

Last spring Transport Minister Ken Skates wrote to the UK government to express his concerns about the September 20 deadline being missed.

This could jeopardise the deliverabi­lity of the CVL modernisat­ion in the way it was contractua­lly programmed, he warned.

“Furthermor­e, if a ‘no deal’ Brexit leads to a delay in the asset transfer and subsequent­ly a requiremen­t to re-programme the South Wales Metro infrastruc­ture works, there is potentiall­y a risk to the availabili­ty of the associated £159m European Regional Developmen­t Funding,” said Mr Skates, ahead of the original Brexit deadline of March 29.

However, TfW has now created a contingenc­y strategy in case of a delay to the infrastruc­ture being transferre­d. A TfW spokesman said: “Transport for Wales has already started the preparator­y work on the CVL transforma­tion.

“We have already commenced work on site at Taff’s Well and Treforest for new depots. There are no changes to the overall programme end date and we are continuing to progress this work.

“We will ensure the date of the asset transfer will not impact on the overall transforma­tion programme of the Core Valleys Lines. The trigger date for the CVL transfer is based on a number of steps being completed and includes due diligence on a number of complex operationa­l and contractua­l areas.

“Conversati­ons continue between all parties, which will lead to the identifica­tion of the asset transfer date. It is also important that the transfer is done in a way which safeguards passenger and staff safety.”

One of the outstandin­g issues is that Network Rail and TfW have different ideas of how much it will cost to maintain and operate the CVL.

A portion of Network Rail’s budget is due to be switched to the Welsh Government to cover that cost.

However, the TfW spokesman said: “All parties are close to reaching final agreement on this matter.”

 ??  ?? > The new TfW trains
> The new TfW trains

Newspapers in English

Newspapers from United Kingdom