‘INDUCED MEANDERING’ UNDERWAY IN ARROYO CHAMISOS

PROJECT AIMS TO SLOW THE WATER AND HELP PREVENT EROSION OF THE BANKS

- BY MARK OSWALD

Santa Fe is getting into “induced meandering.” And it’s not part of a plan for legalizing recreation­al marijuana.

Induced meandering is the governing concept of a major project underway along one of Santa Fe’s major geographic­al features — the Arroyo de Los Chamisos, which stretches from the city’s east side foothills near St. John’s College through the city’s middle and southern sections, and beyond the city limits to the southwest.

The idea is to use often natural-looking structures to get the water rushing through the arroyo during heavy rains to slow down instead of ripping into the banks and causing further erosion, and endangerin­g homes, backyards, roads and the popular walking/bicycling trail along the big nature-made ditch.

“As the water slows down, it will drop the sediment load and deposit it on the bank versus taking soil away,” said Eric Cornelius of Santa Fe Engineerin­g, who’s working on the project.

Huge chunks of the more vertical portions of the arroyo’s banks often fall off into huge mounds of crumbled dirt during rain storms. “Basically, what you want to do is avoid these deep, incised banks,” said Melissa McDonald, city government’s river and watershed coordinato­r.

Work with a budget of $1.6 million is underway at five locations along the arroyo, known colloquial­ly as Arroyo Chamisos, from behind Santa Fe High School west past the Genoveva Chavez Community Center to near the Santa Fe Place mall. Additional sites are targeted in the future.

Cornelius said “the guru” of induced meandering is Bill Zeedyk, a veteran of the U.S. Forest Service, whose New Mexico consulting firm specialize­s in small stream and wetland restoratio­n in the desert Southwest.

Zeedyk’s “An Introducti­on to Induced Meandering” from 2003 states: “The induced meandering method uses artificial instream structures, manipulati­on of streambank vegetation, and the power of running water to expedite channel evolution and floodplain developmen­t. Key components of induced meandering are the proper sizing and spacing of structures and the selective introducti­on or removal of streambank vegetation.”

“What you want is like a floodplain that is long and has vegetation,” said McDonald.

“Let the water do the work,” said Cornelius.

In some of the locations that are part of the Arroyo Chamisos project, once-steep banks have been converted to gentle slopes where “post vanes” have been introduced. In this constructi­on, a series of vertical juniper posts are installed eight feet deep. Rocks are dumped around the bases of the posts, fill dirt is added, then another layer of rocks and more fill, so only the tops of the posts are left above ground.

The result is a structure that works something like a guard rail along a highway, according to Cornelius. “As you’re changing velocity on the road, if you miss the curve and hit that guard rail and bounce back, you do slow down,” he said.

The goal is for something like a ping-pong effect he says, as the slowed water flow is directed to the opposite bank, back and forth through the arroyo, theoretica­lly slow enough to leave sediments behind, build a flood plain, reduce pollutants downstream and increase infiltrati­on into the area aquifer.

“These are really simple techniques,” said McDonald of the post vanes. “Really, anybody can do them, but we’re making them extremely deep. Some arroyos are on private property, and we’re really encouragin­g people to use these techniques themselves.”

Plantings will come

Riparian grasses and chamisa — somehow, that’s what the shrub that is the dominant plant species along the Arroyo Chamisos is called — will be seeded along the arroyo once the earth moving and constructi­on is done.

“All of this work is really responsive to the citizens who wanted a more natural-like arroyo that was beautiful to look at and that was going to be effective toward the concern of ‘Don’t let it damage our homes, and properties and trails,’ ” said McDonald. “They also want it to be inviting to walk by and supportive of wildlife, where we have these kind of natural systems, which have plants growing up between them, versus channelize­d situations.”

She emphasizes, “The top priority is to protect infrastruc­ture and human safety.”

McDonald’s said she’s excited about citizen interest in the arroyo project and cites an “adopt an arroyo” effort undertaken by the Santa Fe Watershed Associatio­n.

It’s not just about picking up trash, said Andy Otto, the associatio­n’s executive director. The program is aimed at developing teams of volunteer residents or from schools to assess arroyos and then come up with solutions, “some things that are not going require a huge permitting process,” he said.

Five teams have been formed and there was a training last fall. “The trash pick-up is important because it gets them out there and owning the arroyo,” Otto said.

Right now, some of the areas where the city’s arroyo work is taking place look less natural than before. The arroyo bed has been flattened out into a big uniform dirt surface, and the chamisa, rocks, tree limbs, other flotsam, sporadic concrete chunks dumped in the past and other junk — a classic Santa Fe bumper sticker says “My other car’s in the arroyo” — are gone, along with island or sandbar shapes in the dirt.

McDonald and Cornelius said that will change.

“They’re going to come in and reseed all these areas where it’s appropriat­e,” McDonald said. “We know that chamisa spreads like wildfire out here.”

Referring to the arroyo bed, she said, “As soon as it rains, it’s all going to shift.”

“An arroyo’s a living system,” Cornelius said. “It’s always changing, it’s meandering, you get what’s called braiding in the arroyo. It’s changing. Every single storm will change it.”

The arroyo “will grow and shrink, grow and shrink,” he said. “This adds a little control.”

Not all parts of the arroyo project use structures as “green” as the unobtrusiv­e the post vanes. For instance, at a drop-off at one of the bridges over the arroyo behind Santa Fe High, big stacks of rock rip-rap bundled in wire are being used on both banks where there has been out-of-control erosion.

Big but attractive boulders are being used to shore up the banks at some points. There are sections where the city doesn’t own enough right of way along the arroyo to do the more sloped designs. McDonald calls the project a “gray-green” combinatio­n to harness the water flow.

“I like to think of it as a slow it, flow it, grow it,” she said. “You want to slow it, flow it where you want it and then grow things.”

 ?? EDDIE MOORE/JOURNAL ?? A rock wall, this one behind the Genoveva Chavez Community Center, is one of the structures being used to stop erosion along the Arroyo de Los Chamisos, which stretches through Santa Fe from east to west. Workers with the RMCI contractin­g firm from...
EDDIE MOORE/JOURNAL A rock wall, this one behind the Genoveva Chavez Community Center, is one of the structures being used to stop erosion along the Arroyo de Los Chamisos, which stretches through Santa Fe from east to west. Workers with the RMCI contractin­g firm from...
 ?? SOURCE: SANTA FE CITY GOVERNMENT ?? This photo shows how rocks are used to shore up juniper posts to create an erosion control structure along the Arroyo de Los Chamisos.
SOURCE: SANTA FE CITY GOVERNMENT This photo shows how rocks are used to shore up juniper posts to create an erosion control structure along the Arroyo de Los Chamisos.
 ??  ?? Erosion along the Arroyo de Los Chamisos, here just west of Santa Fe High School, has been eating away at the banks and threatenin­g infrastruc­ture.
Erosion along the Arroyo de Los Chamisos, here just west of Santa Fe High School, has been eating away at the banks and threatenin­g infrastruc­ture.

Newspapers in English

Newspapers from United States