Albuquerque Journal

WIPP has major projects through summer

- BY ADRIAN C. HEDDEN

CARLSBAD — Numerous infrastruc­ture projects at the Waste Isolation Pilot Plant are on tap into summer, aiming to upgrade the facility and support ongoing operations as emplacemen­t and mining occur simultaneo­usly.

Mining of WIPP’s eighth panel intended to hold nuclear waste permanentl­y in the undergroun­d resumed in January 2018 after work was paused in 2014 following an accidental radiologic­al release in Panel 7.

Panel 8 was expected to be finished by 2020, after the removal of 112,000 tons of salt.

“Resuming mining operations will allow us to continue fully restoring WIPP and fulfilling our important mission of providing a transurani­c waste solution for the (Department of Energy) complex,” said Todd Shrader, then-manager of the Department of Energy’s Carlsbad Field Office.

But airflow in the mine was restricted, insufficie­nt to allow mining and waste emplacemen­t in Panel 7 simultaneo­usly.

To rectify this, Nuclear Waste Partnershi­p, the contractor hired by the DOE to oversee daily WIPP operations, took on a $288 million rebuild of WIPP’s ventilatio­n system.

Known as the Safety Significan­t Confinemen­t Ventilatio­n System, the project was intended to increase airflow from 160,000 cubic feet per minute to 540,000 to allow emplacemen­t and mining to occur at the same time, said a news release last week from the DOE’s Office of Environmen­tal Management.

It will be powered by six 1,000-horsepower fans spread among two buildings cleaning the air as it is sent to the undergroun­d for workers to breathe, and drawn back up to the surface as exhaust.

The system was expected to be completed by 2021.

“The SSCVS is critical to EM’s plans to increase shipments of transurani­c waste to WIPP from cleanup sites across the DOE complex,” the release said.

WIPP personnel are engaged in multiple other infrastruc­ture projects this summer, many related to airflow.

Here are some of the biggest ongoing at the site:

Salt-reduction building — Air coming from the undergroun­d will first meet

here where salt, dust and moisture is removed using filtering machines and other equipment. Workers recently completed the undergroun­d piping and are excavating an area to provide a collection pool for salt and water removed from the air.

Filter building — After the saltreduct­ion building, air is put through several increasing­ly fine filters, trapping contaminan­ts before being released into the air. Subsurface excavation is underway.

Fabricatio­n assembly building — The preenginee­red building was delivered to the WIPP site, and excavation began for its foundation. Components of the SSCVS will be built in this building.

Utility shaft — One of five shafts descended to about 2,150 feet in the undergroun­d, and land was cleared for this utility shaft. It’s 30 feet in diameter, making it the largest at WIPP. The new shaft will provide air intake and a third access point to take materials down into the mine. It was planned to be complete by August 2022.

Bypass road — The road will direct traffic away from the WIPP site during constructi­on of the utility shaft. It was expected to be finished by the end of the year.

Lighting protection system — “Dandelions­haped” arrays are to be installed on top of light poles at the WIPP site, to prevent a direct lighting strike. This summer’s upgrade will fill in gaps in the current system. Lighting hasn’t struck within the site’s fence line in 30 years, the release said.

Fire-protection loop — Workers are digging into the soil to replace several failed valves ahead of adding a new fire waterline. The loop will include new tanks, a pump house and hydrants for fighting any fires that occur at WIPP. This project was expected to be finished by the end of 2020.

 ?? COURTESY OF OFFICE OF ENVIRONMEN­TAL MANAGEMENT ?? This trench will serve contractor trailers at the Safety Significan­t Confinemen­t Ventilatio­n System project east of the WIPP site.
COURTESY OF OFFICE OF ENVIRONMEN­TAL MANAGEMENT This trench will serve contractor trailers at the Safety Significan­t Confinemen­t Ventilatio­n System project east of the WIPP site.

Newspapers in English

Newspapers from United States