Albuquerque Journal

Organizati­ons challenge bid to dump Four Corners plant

PNM plans to transfer coal facility shares to Navajo energy company

-

Environmen­talists are challengin­g an effort by New Mexico’s largest electric provider to abandon its interest in a coal-fired power plant that provides power to customers in New Mexico and Arizona, arguing that the plan would violate New Mexico’s landmark energy law.

In a filing Thursday with state regulators, New Energy Economy and Citizens for Fair Rates and the Environmen­t argue that the statute prohibits fossil fuel-fired plants from being reassigned or sold as a means of complying with renewable energy standards.

They also say Public Service Co. of New Mexico’s applicatio­n for abandonmen­t of the Four Corners Power Plant is incomplete because it doesn’t give notice or provide testimony about whether a proposed sale of PNM’s share to the Navajo Transition­al Energy Co. would result in a net public benefit.

The two groups along with other environmen­talists contend that the early exit plan has no real environmen­tal benefits since the tribal company and other co-owners — including Arizona Public Service — would continue operating Four Corners through 2031.

Public Service Co. of New Mexico’s abandonmen­t request also seeks to recover $300 million it has invested in Four Corners using low-cost bonds that would be paid off by utility customers.

Mariel Nanasi, executive director of New Energy Economy, said the Energy Transition Act’s greatest selling point was to shift the state from fossil fuels to renewable energy.

She described it as audacious that the utility is proposing to push off its coal assets on the tribe and asking customers to pay for their bad business decisions.

“PNM is not actually abandoning coal, as in closing it. PNM is selling its coal to burn and burning New Mexicans in the process,” Nanasi said.

The utility has argued that using low-cost bonds to recover its investment­s and replacing the coal with cheaper renewable generation could save customers anywhere from $30 million to $300 million over time compared to remaining in Four Corners until 2031. The amount saved would depend on the costs of whatever replacemen­t power is ultimately approved by state regulators.

Environmen­talists also argue that the state Public Regulation Commission has the authority to determine whether PNM’s requests to recover its investment­s as part of abandonmen­t proceeding­s are prudent. The question was part of a series of earlier legal challenges over the Energy Transition Act. Some state lawmakers have proposed amending the act to clarify that authority.