Arkansas Democrat-Gazette

Texas contractor put on design team for $58M Cantrell/I-430 job

- NOEL OMAN

A Fort Worth contractor has been tabbed to help design the estimated $58.3 million project to remake the congested Cantrell Road/ Interstate 430 interchang­e in west Little Rock.

Kiewit Infrastruc­ture South is working on the first project the Arkansas Department of Transporta­tion chose to build under a constructi­on method new to Arkansas but used with success in other states.

Under the constructi­on manager/contractor method, Kiewit will work with a Transporta­tion Department team to design the project to complete it in a timely manner while managing traffic through the interchang­e.

“The constructi­on manager will work side by side with the design team,” said Scott Bennett, the department director.

That section of Cantrell Road, which is also called Arkansas 10, is the busiest noninterst­ate thoroughfa­re in the state, with up to 54,000 vehicles traveling between Pleasant Valley and Pleasant Ridge roads every day.

Working with a contractor will allow the agency design team to make “informed decisions on design options based on the contractor’s expertise,” according to the Federal Highway Administra­tion.

Once the project is designed, Kiewit will have the first opportunit­y to submit a bid to do the work. Its bid

will be compared with a project cost developed by an independen­t estimator the Transporta­tion Department also will hire. If both figures are within 10 percent of each other, Kiewit will build the project.

If the difference between the two figures exceeds 10 percent, the project will go through the traditiona­l bidding process, in which projects are designed and then contractor­s bid. The contractor that submits the lowest bid will be selected for the job. Kiewit will be allowed to participat­e in that process as well.

Kiewit was one of two contractor­s that submitted qualificat­ions to manage and construct the project under Act 809 of 2017, which allows the department to use the method on up to three pilot projects not to exceed $200 million in total cost. Only one project at a time can be built under the manager/contractor method.

Agency staff members recommende­d Kiewit over McGeorge Contractin­g Co. of Pine Bluff.

Kiewit’s selection Tuesday by the Arkansas Highway Commission came less than five months after the department announced the plan to improve traffic flow on that section of Cantrell, which has seen surging traffic and increased developmen­t. A study of the corridor has projected that 76,000 vehicles will be using the corridor daily in 20 years.

The project is centered on a single-point urban interchang­e design in which the section of Cantrell, widened to six lanes from four, will have traffic go over the North Rodney Parham Road intersecti­on rather than, as it does now, through it.

The elevated roadway is similar to the ramp that carries traffic on Interstate 630 over South Shacklefor­d Road in the Interstate 430/Interstate 630 interchang­e.

The “single point” in the interchang­e design would be underneath Cantrell at North Rodney Parham. One traffic signal would control traffic moving onto or off Cantrell, which would allow motorists going east and west on Cantrell to avoid stopping at a light to accommodat­e North Rodney Parham traffic, a feature that is a source of much of the congestion in the corridor.

The design also includes a feature popularly known as a “Texas turnaround,” which will allow drivers traveling south on I-430 to go east on Cantrell. Motorists actually would travel west for a short distance, then make what amounts to a U-turn back to the east.

The Texas turnaround would replace a loop ramp that traffic now uses to go from southbound I-430 to eastbound Cantrell and would eliminate an element that has the southbound I-430 traffic merging into the same lane used by eastbound Cantrell traffic to access I-430 north.

The new interchang­e also will feature a traffic circle north of Cantrell and opposite North Rodney Parham that would serve traffic for the Walton Heights neighborho­od, River Mountain Road and a bank and church facing Cantrell.

Kiewit already is well-acquainted with the interchang­e. It was the contractor that recently completed the $22.9 million constructi­on of a ramp from Cantrell westbound to I-430 northbound.

Bennett said Kiewit personnel on the project were well-received by people in a neighborho­od that adjoins the ramp.

“One of the neighbors threw a fish fry for the workers,” he said. “The neighbors were happy with the way things were going.”

The commission also accepted the department recommenda­tion on the selection of Innovative Contractin­g & Engineerin­g of Las Vegas to serve as an independen­t cost estimator that will work with the contractor and the design team.

The company will provide a “detailed cost estimate from a contractor’s perspectiv­e to ensure that the department can negotiate effectivel­y with the [constructi­on manager/ contractor] and provide the best value to the department.”

The commission also voted to send out a request for proposals for a second independen­t cost estimator that will observe the design work but keep its cost estimate from Kiewit. It is that estimate that will be used to verify whether Kiewit’s bid is within 10 percent of the independen­t estimate.

 ??  ??

Newspapers in English

Newspapers from United States