Arkansas Democrat-Gazette

Illness pauses 1 NW road project; others roll on

-

BENTONVILL­E — Work to complete the Bella Vista Bypass is close to schedule, but the primary contractor paused one project after an employee tested positive for the coronaviru­s.

The delay isn’t critical to the larger picture of completing the bypass project, said Steve Lawrence, District 9 engineer with the Arkansas Department of Transporta­tion.

Lawrence said Emery Sapp & Sons told the department May 18 that the company needed to stop work after an employee on the Interstate 49 interchang­e project in north Bentonvill­e tested positive. Other projects weren’t affected.

Sapp & Sons is the primary contractor for the interchang­e, new lanes of the bypass from Benton County Road 34 to the state line, and Missouri’s portion of the project. The 2.5-mile stretch of road in Arkansas will cost about $35.5 million.

Robert Gillis with Sapp & Sons said work on the interchang­e will resume after the Memorial Day weekend.

“We paused the project to make sure we could evaluate the situation,” Gillis said. “After doing all of our tracing, due to weather, that employee had only been on the project one day in the last three and a half weeks, and he was already seven days from being on the job when he found out that he had tested positive.”

Transporta­tion Department officials will look at the Sapp & Sons contract later to determine whether the company should be allowed more time to complete the project because of delays caused by unforeseen circumstan­ces. Companies risk the loss of incentives or added costs if the work isn’t completed on time.

“A lot of times, what we’ll do with something like this is the contractor may put us on notice that they are anticipati­ng a delay, especially on something of this nature where it’s out of their control,” Lawrence said. “When we get through whatever it is, then we go back and look at the time and evaluate how much additional time, if any, is warranted.”

Missouri awarded a $58.7 million contract April 1 to Sapp & Sons to build the final 5 miles of I-49 between Pineville and the state line in McDonald County. Work started May 11, with completion expected by Sept. 30, 2021.

“The contractor is currently ramping up earthwork operations and also getting started building some of the drainage structures,” said Craig Switzer, transporta­tion project manager with the Missouri Department of Transporta­tion. “We don’t anticipate a delay to our completion date.”

Switzer said the person involved in the coronaviru­s case on the Arkansas side didn’t come into contact with any crews on the Missouri side.

The 19-mile bypass will allow motorists to circumvent Bella Vista to the west and south on a four-lane interstate. The project is also known as the Interstate 49 Missouri/Arkansas Connector, a nod to its regional importance.

Tim Conklin, assistant director at the Northwest Arkansas Regional Planning Commission, said keeping projects moving is vital, given the region is forecast to have nearly 1 million people by 2045.

“Major infrastruc­ture highway projects take decades to plan and design, years to identify program funding and multiple years to construct,” Conklin said. “Northwest Arkansas continues to play catch-up with infrastruc­ture projects to provide the capacity and desired connectivi­ty for the region. Specifical­ly, I-49 provides interstate access for freight and people.”

Arkansas officials awarded bids in July and broke ground in October on two sections needed to fill missing links on the Arkansas side.

The two projects are the last 2.5 miles from Hiwasse to the state line and the single-point urban interchang­e to replace the roundabout at I-49 and U.S. 71 in north Bentonvill­e where the new highway heads west. The estimated cost of the two projects is just more than $100 million. Sapp & Sons is the primary contractor on both.

A third project, adding the remaining 6 miles of lanes on the Arkansas side, has been underway for some time. Kolb Grading is the primary contractor on that $52.6 million job. Lawrence said Kolb is slightly behind schedule, but it isn’t due to the covid-19 pandemic.

The goal is for Arkansas and Missouri to each build their parts and meet at the state line in late 2021, or early 2022 at the latest, according to regional planners.

The ultimate goal is completion of the 278-mile section of interstate between Fort Smith and Kansas City, Mo. Bella Vista is the only stretch where traffic has to leave I-49 and continue on U.S. 71 to travel. Allowing motorists to bypass Bella Vista and its multiple traffic signals should reduce travel times and improve safety, planners have said.

Lawrence said work on the interchang­e at Exit 85’s Walton Boulevard in Bentonvill­e and Walnut Street in Rogers is lagging slightly as a result of a shortage of available material because of the virus.

Mitchell Archer, constructi­on engineer with District 9, said several contractor­s told the department that if they see slowdowns, they might make claims later for more time to complete their projects without penalty.

“Most all of our jobs, we’ve had to make modificati­ons as far as distancing, sanitation, but in general we haven’t seen any significan­t slowdowns on any of our work until the incident on the interchang­e job,” Archer said.

Lawrence said department employees have remained on the job site every day inspecting work.

“Our ArDOT forces are doing an excellent job adapting to the conditions that were given them as far as social distancing and staying away from each other,” Archer said. “They’re sanitizing their equipment and their trucks. They’re staying working, but they’re not congregati­ng. Some work from home; some work from their field shacks. They’re doing a good job of taking care of business.”

Newspapers in English

Newspapers from United States