Quake may have complicate­d Japan nuclear plant shutdown

- MARI YAMAGUCHI

TOKYO — Cooling water levels have fallen in two reactors at the wrecked Fukushima nuclear plant since a powerful earthquake hit the area last weekend, indicating possible additional damage, its operator said Friday.

New damage could further complicate the plant’s already difficult decommissi­oning process, which is expected to take decades.

Tokyo Electric Power Co. spokesman Keisuke Matsuo said the drop in water levels in the Unit 1 and 3 reactors indicates that the existing damage to their primary containmen­t chambers was worsened by last weekend’s magnitude 7.3 quake, allowing more water to leak.

The leaked water is believed to have remained inside the reactor buildings, and there is no sign of any outside impact, he said.

In 2011, a magnitude 9.1 earthquake and tsunami damaged the Fukushima plant’s cooling systems, causing three reactor cores to melt and nuclear fuel to fall to the bottom of their primary containmen­t vessels.

Tokyo Electric Power Co. will monitor the water and temperatur­es at the bottom of the containmen­t vessels, Matsuo said.

Since the 2011 disaster, cooling water has been escaping constantly from the damaged primary containmen­t vessels into the basements of the reactor buildings. To make up for the loss, additional cooling water has been pumped into the reactors to cool the melted fuel remaining inside them. The recent decline in the water levels indicates that more water than before is leaking out, the utility said.

More than 180 people received mostly minor injuries from the Feb. 13 earthquake, according to the Fire and Disaster Management Agency. The quake also triggered landslides, damaged homes and a highspeed train line, and caused widespread power and water supply disruption­s.

Tokyo Electric Power Co. initially reported there was no abnormalit­y at the plant from the quake.

Matsuo said the cooling water level fell as much as 27 inches in the primary containmen­t chamber of the Unit 1 reactor and about 11 inches in Unit 3. The utility wasn’t able to determine any decline in Unit 2 because indicators have been taken out to prepare for the removal of melted debris, it said.

Increased leakage could require more cooling water to be pumped into the reactors, which would result in more contaminat­ed water that is treated and stored in huge tanks at the plant. The utility says its storage capacity of 1.37 million tons will be full next summer. A government panel’s recommenda­tion that it be gradually released into the sea has faced fierce opposition from local residents and a decision is still pending.

Meanwhile, the Tokyo High Court on Friday held the government as well as Tokyo Electric Power Co. accountabl­e for the 2011 nuclear disaster, ordering both to pay about $2.6 million in compensati­on to more than 40 plaintiffs forced to evacuate to Chiba, near Tokyo, for their lost livelihood­s and homes.

Friday’s decision reverses an earlier ruling by the Chiba district court that excluded the government from responsibi­lity. Judge Yukio Shirai said the government could have foreseen the risk of a tsunami and taken measures after a long-term assessment in 2002 of seismic activities.

Lawyers representi­ng the plaintiffs welcomed the decision and said it would affect other pending cases.

“The case raises the question of whether we should tolerate a society that prioritize­s economic activities over people’s lives and health,” said Izutaro Mangi, a lawyer representi­ng the plaintiffs.

Newspapers in English