Fukushima disposal plan fully approved

Wastewater release set for next year

- MARI YAMAGUCHI

The plan will become official after a 30-day public review, a formality that is not expected to overturn the approval.

TOKYO — Japan’s nuclear regulator on Wednesday approved plans by the operator of the wrecked Fukushima nuclear plant to release its treated radioactiv­e wastewater into the sea next year, saying the outlined methods are safe and risks to the environmen­t minimal.

The plan was submitted by the Tokyo Electric Power Company Holdings in December based on the government’s decision last year to release the wastewater as a necessary step for the ongoing plant cleanup and decommissi­on.

A massive earthquake and tsunami in 2011 destroyed the Fukushima plant’s cooling systems, causing the meltdown of three reactors and the release of large amounts of radiation. Water that has been used to cool the three damaged reactor cores, which remain highly radioactiv­e, has since leaked but was collected and stored in tanks.

There is still concern in the community and neighborin­g countries about the potential health hazards of the release of the wastewater that includes tritium — a byproduct of nuclear power production and a possible carcinogen at high levels.

The government and TEPCO say more than 60 isotopes selected for treatment can be lowered to meet safety standards, except for tritium, but that it is safe if diluted. Scientists say impact of long term low-dose exposure to the environmen­t and humans are unknown, and that tritium can have a bigger impact on humans when consumed in fish than in water.

Japan nuclear authority chairman Toyoshi Fuketa said that the plan is made conservati­vely so the radiation impact on the environmen­t could be still below the legal limit in case of any thinkable risks.

Under the plan, TEPCO will transport water that has been treated to below releasable levels through a pipeline from the tanks to a coastal facility, where the water is diluted with seawater.

From there, the water will enter an undersea tunnel to be discharged at a point about 0.6 mile from the plant to ensure safety and minimize the impact on local fishing and the environmen­t, according to TEPCO.

The plan will become official after a 30-day public review, a formality that is not expected to overturn the approval.

The green light came just as the Internatio­nal Atomic Energy Agency’s Director Mariano Grossi arrived in Japan for meetings with top officials to discuss the plan, which has received internatio­nal attention.

Fuketa will meet with Grossi on Friday after the IAEA director’s visit to the Fukushima plant on todayand meetings with other Japanese officials.

The government and TEPCO plan to begin gradually releasing the treated water in spring 2023.

The contaminat­ed water is being stored in about 1,000 tanks at the damaged plant, which officials say must be removed so that facilities can be built for its decommissi­oning. The tanks are expected to reach their capacity of 1.37 million tons next year — slower than an earlier estimate of later this year.

Japan has sought the IAEA’s assistance to ensure the water release meets internatio­nal safety standards, and to reassure local fishing and other communitie­s as well as neighborin­g countries.