Arkansas Democrat-Gazette

Hot Springs leaders hold line on costs for treatment plant

- DAVID SHOWERS

HOT SPRINGS — Action the Hot Springs Board of Directors took last week intends to hold the line on costs for the water treatment plant the city is building off Amity Road.

A resolution the board adopted at its March 7 business meeting approved a $1.59 million change order, raising the original $34.95 million cost of the new plant to $39.86 million and eliminatin­g an amendment agreed to in September that made the city responsibl­e for price escalation­s in materials, supplies and labor.

“Upon receipt of any such price increase, the contractor shall provide notice of the price increase to the city and the agreement shall be increased to incorporat­e such increase in price plus a markup of 15%,” according to the first paragraph of the addendum The Sentinel-Record first reported on in December.

A $3.32 million change order the city agreed to last fall raised the cost of the TOLM Group’s constructi­on contract for the 15 million-gallon-a-day plant to $38.27 million, about $15 million more than the city and its contract engineers had estimated before the July bid opening.

The higher-than-expected bids put the Lake Ouachita water supply project over budget, leading the board to approve a rate increase in November that’s servicing more than $45 million in new water fund debt.

The $4-a-month increase, which goes into full effect in November, for city utility customers inside the incorporat­ed area followed a series of rate increases that took effect from 2018 to 2021. The latter services the $109 million bond issue the board authorized in June 2020.

“With this change order to the contract, it’s still $8 million less than the next-lowest bidder,” Major Capital Projects Manager Todd Piller said, referring to the $47.60 million bid CDI Contractor­s of Little Rock submitted in July, told the board.

McKee Utility Contractor­s of Oklahoma bid $54.35 million, the highest of the three the city received.

The $3.32 million change order extended the plant completion date from spring 2024 to late 2025. Piller told the board last week that delivery times are more than a year for some equipment and materials. The city has blamed supply chain disruption­s for increasing what was a $106 million project in 2019 to more than $150 million.

The change order approved last week will be paid for from the proceeds of a $45 million bond issue that the board authorized in November. Funds were deposited into the constructi­on account at the end of January, but the city said no money had been spent as of last week.

The $1.25 million addition to Belt Constructi­on’s $9.17 million raw waterline contract the board approved last month had yet to be debited from 2022 bond funds.

In addition to the nearly $40 million cost of building the new plant, contracts totaling more than $6 million have been awarded for site preparatio­n and a 3 million-gallon clear well at the 33-acre Randall Road site the city acquired in 2019. Piller told the board last week that the 160-foot diameter clear well recently passed a leak test.

It will hold treated water and high-service pumps will distribute via the large-diameter finished waterline. Natgun Corp. was awarded the $4.19 million contract in 2021. Kajacs Constructi­on completed the first 2.5-mile segment of the 13-mile finished waterline in 2021. It was awarded the $4.43 million contract in 2020.

CDI Contractor­s completed the $2.02 million site prep. It included building two 4 million-gallon backwash ponds for treated water that will be discharged into a nearby creek after it’s used to clean the plant’s filters.

Newspapers in English

Newspapers from United States