Arkansas Democrat-Gazette

Zion Road nearly done, city says

- STACY RYBURN

FAYETTEVIL­LE — Work on Zion Road in Fayettevil­le is officially more than a year behind schedule, but the toughest parts are finished, according to the city official overseeing the project.

Once finished, Zion will have three car lanes with a trail on the north side and a sidewalk on the south side from Vantage Drive to Crossover Road. There will be one car lane in each direction east and west and a turning lane. A roundabout at the intersecti­on with Old Missouri Road is done.

The road east of Old Missouri has been widened from about 20 feet to 30 feet, with trail and sidewalk replacing ditches on the north and south sides of Zion, respective­ly.

Crews just finished installing a sewer main from Taliesin Lane just east of the roundabout to near Randal Place, which required digging more than 20 feet undergroun­d in problemati­c soil, said Chris Brown, the city’s public works director.

There are two ways crews go about doing deep trench work. One is to dig deep slopes so the trench comes in at an angle, which requires a lot of room. The other way is to put up temporary walls to prevent the trench from caving in. Crews initially tried putting up temporary walls, but the soil kept caving in before they could install the walls. So they ended up using a combinatio­n of both methods, which is a reason the sewer line work took so long, Brown said.

The weather also was uncooperat­ive for several days throughout the project, with major snow and freezing events this winter, he said. Additional­ly, the pandemic has caused labor and material shortages, meaning Tri Star, the contractor, hasn’t had enough employees for the project and has experience­d delays, he said.

The section east of the roundabout to Randal Place has gravel on it and just needs paving and striping now, Brown said. That should happen in the next couple of weeks, he said.

Next, crews need to install a sewer line from Randal Place to Crossover Road. The work shouldn’t take as long as the previous sewer line because the crews will dig at a shallower depth, enabling them to install more pipe at a time, Brown said.

Work began in November 2020 and was initially set to wrap up in February 2022. The contractor’s scheduled completion date is the end of May.

The project has been a pain for neighbors in the Lakewood subdivisio­n north of Zion Road, resident Tom New said.

Streets in the subdivisio­n are narrow. While crews were working on the deep sewer line, trucks frequently would come into the neighborho­od, hitting mailboxes, tree limbs and trees, New said.

Cut-through traffic has subsided a bit since the city put a detour sign to Randal Place a few weeks ago, but it hasn’t stopped completely, New said. He suggested the city place more obvious signs directing drivers to Randal Place and to discourage cars from coming through the neighborho­od.

The project is also over budget, Brown said. The original estimated cost was $6.8 million, and the project is sitting at about $7.4 million.

Newspapers in English

Newspapers from United States