Springdale panel favors contracts for road extension

- TOM SISSOM

SPRINGDALE — A contract for the second phase of the planned extension of West Emma Avenue was endorsed Wednesday by members of the Springdale City Council.

Meeting as a committee, the council members recommende­d approval of two resolution­s, one authorizin­g a $16.5 million constructi­on contract and the second a $535,000 contract for constructi­on services on the project.

The City Council will consider the resolution­s when it meets Tuesday.

The council members recommende­d awarding the constructi­on contract to Crossland Heavy Contractor­s. The company submitted the low bid on the project in December, with its bid coming in at $16,539,926.50.

The project is part of the city’s 2023 bond issue.

The second contract recommende­d for approval is for constructi­on services on the same project. The contract with Garver engineerin­g firm is for an amount not to exceed $535,000. According to informatio­n from the city, the constructi­on services include three months of part-time field coordinati­on during utility relocation, about 11 months of full-time inspection during bridge constructi­on and about three months of part-time inspection during the remaining roadway constructi­on.

The city has had a $1.2 million contract with Garver to do constructi­on services on the first phase of the project.

According to informatio­n from the city’s website, the project includes extending Har-Ber Avenue from 48th Street to Gutensohn Road. The east end of the proposed street will be at the West Emma Avenue and Gutensohn Road intersecti­on, and the west end will be at the intersecti­on of 48th Street and Har-Ber Avenue. The project will include a bridge across Interstate 49, three lanes with a center turn lane (two lanes across the bridge), sidewalk, a 12-foot side path, and traffic signals at 48th Street, 40th Street and Gutensohn Road. Phase 1 of the project consists of improvemen­ts from Gutensohn to 40th Street, which is approximat­ely 0.75 miles. The cost of phase 1 is put at almost $10 million.

Phase 2 includes the constructi­on of Har-Ber Avenue from 48th Street east to 40th Street and the widening of 40th Street, including an overpass above I-49.