Austin American-Statesman

Audit shows city estimates often too low

Nearly one-third of projects reviewed came in at least 50% higher.

- By Philip Jankowski pjankowski@statesman.com

Austin officials initially priced the Shoal Creek storm drain improvemen­t project at $1 million. But when the final bill was paid, the project actually cost Austin taxpayers about $7 million.

The renovation­s to City Hall and the City Council Chambers to make room for the larger, 11-member council that took office in 2015 were originally priced at $1.4 million. The costs soared to $6.4 million.

Those two projects were just a few in an audit of Austin’s Public Works Department released last week that found almost one-third — 29 percent — of the 48 projects it reviewed had costs balloon at least 50 percent higher than the staff ’s original estimates.

“The City often did not prepare accurate project cost estimates or collect reliable data to do so,” the audit said.

The Public Works Department agreed with most of the findings in the audit and noted it could conduct additional training on estimating the costs of projects, and that the department has been making improvemen­ts since Octo-

ber 2016. It estimated full implementa­tion of improvemen­ts by October 2018.

Public Works Director Richard Mendoza also noted in a memorandum responding to the audit that initial cost estimates are made with varying amounts of informatio­n about the project.

The audit of Austin’s capital project delivery was among the inquiries the city auditor’s office had scheduled for this year after previous audits, including one of the airport’s expansion, unearthed issues, according to a city spokesman.

Auditors reviewed a sample of projects and did not seek comprehens­ive data on the difference between initial cost estimates and final price tags for all capital improvemen­t projects. Nor did auditors examine how these projects ballooned from the staff ’s original cost considerat­ions.

But the audit found flaws in the Austin Public Works Department’s quality control review process. In some cases, the department’s staff ignored the quality review process altogether, which sometimes led to change orders or increased project costs to fix issues that should have been identified earlier.

Of a sample of 48 projects, the audit found that 18 — 38 percent — were never submitted for review to the Public Works Department’s division that checks quality control. Those projects included a pedestrian bridge and the Turner Roberts Recreation Center.

And of those sample projects that were submitted for review, that division failed to look over quality control plans for 39 percent of them.

In other cases, high-profile projects faced expedited or limited reviews.

For instance, management authorized staff to ignore comments made by the quality control division about the designs for the new Central Library.

“As a result, staff submitted designs for bid and constructi­on without subjecting them to the full quality management process,” the audit said.

The library project saw its costs grow from $90 million to $125 million as its opening was delayed repeatedly. It is set to open Oct. 28, nearly a year after the original target date.

In another unspecifie­d case, a project manager successful­ly persuaded management to forgo quality management inspection­s because it would create “burdensome” delays, the audit said.

The Public Works Department appears to have improved its review process in recent years, but the audit still found a substantia­l number of projects did not undergo the full quality review process, which includes three reviews of designs along with the quality control plan.

In the new Central Library’s case, the auditors found that two oversights in the design phase led to about a $32,000 cost increase.

For instance, the city had to fork over $14,557 more for the library project after a contractor discovered that design documents did not provide a power supply for portions of the library’s fire protection system.

“Many of the change estimates (and accompanyi­ng cost increases) we reviewed for the New Central Library stemmed from missing, unclear or conflictin­g items in the New Central Library designs that a quality review may have caught,” the audit states.

In every case auditors reviewed, the Public Works Department also allowed contractor­s to begin performing unauthoriz­ed work before those change orders were approved. For example, contractor­s performed $66,500 of work in 2015 on an erosion control wall for the Waller Creek Tunnel without approval. This happened five months after the Public Works Department had assured the City Council that it would follow the change order process, the audit said.

The audit also questioned the autonomy of project managers, who can approve new work with little oversight. In one unspecifie­d project, a program manager agreed to allow $82,653 of steel work for the Central Library to be performed despite the manager believing the city was not getting a fair price. The manager ultimately agreed because he thought it would be better to accept the costs than face further delays in the beleaguere­d project.

The city has little it can do to recoup costs and could face litigation if the Public Works Department backed out on paying for the contractor’s completed work, the audit said.

In response to the audit, the Public Works Department’s staff said they would implement a leaner quality management process and streamline the change order process with the input from an already existing city staff team.

 ?? RALPH BARRERA / AMERICANST­ATESMAN 2014 ?? Renovation of City Council offices and chambers, shown in 2014, grew to about $5 million more than officials originally expected, a recent audit found.
RALPH BARRERA / AMERICANST­ATESMAN 2014 Renovation of City Council offices and chambers, shown in 2014, grew to about $5 million more than officials originally expected, a recent audit found.
 ?? RICARDO B. BRAZZIELL / AMERICAN-STATESMAN 2016 ?? The new downtown Austin Central Library project saw its costs grow from $90 million to $125 million as its opening was delayed repeatedly. It is set to open Oct. 28, nearly a year after the original target date.
RICARDO B. BRAZZIELL / AMERICAN-STATESMAN 2016 The new downtown Austin Central Library project saw its costs grow from $90 million to $125 million as its opening was delayed repeatedly. It is set to open Oct. 28, nearly a year after the original target date.

Newspapers in English

Newspapers from United States