Baltimore Sun

Metro to partially close for weeks of maintenanc­e

Free shuttle buses will run during 23-day shutdown

- By Colin Campbell

The Baltimore Metro subway, which carries about 45,000 people a day, will be partially shut down for more than three weeks starting July 22 for what the Maryland Transit Administra­tion called critical maintenanc­e work, the MTA said Tuesday.

The closure of part of the nearly 33-year-old system comes amid growing problems for the nation’s aging mass transit infrastruc­ture as exemplifie­d by the Washington Metro, which has experience­d several breakdowns this year and faces a significan­t backlog of maintenanc­e and repairs.

Service between Mondawmin Mall and Milford Mill on the Baltimore Metro will be shut down from July 22 through Aug. 14, closing the Reistersto­wn Plaza, Rogers Avenue and West Cold Spring stations. The MTA will run free shuttle buses between those stations for the duration of the project. A separate express shuttle will run

directly between the Milford Mill and Mondawmin stations.

Service will continue between Milford Mill and Owings Mills, and between Mondawmin, downtown and Johns Hopkins Hospital.

“This necessary and critical rail work will further enhance service safety and reliabilit­y, and allow trains to move faster through this corridor of the Metro track,” said Sandy Arnette, a spokeswoma­n for the MTA, which first announced the closure in March.

The $16 million project involves reconstruc­ting three interlocki­ngs, the devices that allow trains to cross from one track to another, the MTA said. Crews also will replace old rails, improve the stations and clean, the administra­tion said.

Arnette said the work and the shutdown have been planned for more than a year, but the administra­tion waited to announce it to the public “because people could forget.”

Mike McMillan, vice president of the Amalgamate­d Transit Union Local 1300, which represents the subway’s workers, called the repair work badly needed — and nearly two years overdue.

One of the three outdated interlocki­ngs, on the southbound tracks between the West Cold Spring and Mondawmin stations, was in such disrepair that for the past year operators have slowed trains down to 20 mph from their normal 50 mph to avoid a derailment, McMillan said.

The MTA ordered the slowdown in accordance with industry standards, Arnette said.

“When track is observed to exhibit worn conditions, it is judged as having a lesser classifica­tion rating and safe train operation can be achieved by lowering the operating speed commensura­te with the wear characteri­stics,” Arnette said in a statement.

McMillan called the practice a “BandAid” for a larger problem.

Aging railroad ties, the wooden supports laid perpendicu­lar under the rails, were splitting in some sections, said McMillan, a former train operator and station attendant. The splitting ties have long been a “serious concern” of subway workers because of the possibilit­y of a derailment.

Safety is the MTA’s priority, Arnette said, and the interlocki­ng equipment is simply nearing the end of its useful life.

Bill Bralove, a former member of the MTA Citizens Advisory Committee, said he was flabbergas­ted by the administra­tion’s plan.

“To just turn it off for three weeks?” said Bralove, 65, of Randallsto­wn. “It’s incredible to me how they think people can rearrange their jobs, their schedules, their lives in the hottest part of the season because the MTAhas failed to maintain this system for 25 years.”

The MTA is suggesting riders who need to traverse the closed section plan for an extra hour each way. The shuttles — 70 yellow school buses — will run at 10-, 20and 30-minute intervals, officials said, based on the time of day.

The administra­tion opted to do the work during the summer because the system is regularly used by students during the school year.

“We chose to schedule this maintenanc­e work during the summer when schools are closed and many people are on vacation to help minimize the impact on our riders,” Arnette said.

Bralove, who takes the subway several times a week for a volunteer job at the attorney general’s office in downtown Baltimore, said he plans to take the three weeks off rather than wait an extra hour both ways and ride a school bus. But he wonders what the shutdown will mean for people who don’t have that option and aren’t able to get to their jobs on time.

MTA officials “wipe it off like it’s a little inconvenie­nce for a day or two,” he said. “It’s three weeks.”

The 23-day shutdown period is just a day shy of the longest planned Washington Metro closure as officials there undertake an aggressive, yearlong overhaul of the system following years of neglect and breakdowns.

The repairs in Baltimore, Bralove said, are anything but routine.

“That’s like going in and having a heart and lung transplant and saying, ‘I’ve had my annual checkup,’ ” he said. “They’ve taken routine maintenanc­e and delayed it until it becomes an emergency maintenanc­e problem.”