Officials hail partial bridge opening

- By Colin Campbell cmcampbell@baltsun.com twitter.com/cmcampbell­6

City officials touted the partial opening of the Central Avenue Bridge on Monday, connecting the Harbor East and Harbor Point developmen­ts — a project that was delayed more than a year and a half and won’t be finished until the end of September.

The bridge, funded with $10 million of the city’s $107 million tax-increment financing for Harbor Point, was supposed to be finished in time for the opening of Exelon’s $270 million, 20-story building in November 2016.

Mayor Catherine E. Pugh, City Council President Bernard C. “Jack” Young and Transporta­tion Director Michelle Pourciau walked across the bridge Monday. It opened to two lanes of traffic, pedestrian and bicycle access; another two traffic lanes will be added in the next three months.

Pugh called the project a success, and said it will create better access to the 3 million square feet of mixed-use space planned for the 27-acre Harbor Point site on the east side of downtown.

“This is a really important corridor for us,” she said. “Opening up this bridge is essential to the developmen­t and the community as a whole, coming together, working together, and at least providing the opportunit­ies for us to engage from one section of our city to the other.”

The bridge creates a second road connection to the Harbor Point peninsula, which previously could be reached only via South Caroline Street. Other improvemen­ts to the Central Avenue corridor are planned.

Pourciau attributed the year and a half delay in building the bridge to “latent conditions,” a constructi­on term for unforeseen problems with a building site. She did not specify what those conditions were. Mayor Catherine E. Pugh, center, and Transporta­tion Director Michelle Pourciau, left, walk Monday across the Central Avenue Bridge connecting Harbor Point and Harbor East. The bridge is expected to be opened to another two lanes of traffic by the end of September.

The soil and groundwate­r beneath Harbor Point are riddled with toxic chromium entombed beneath a cap of clean soil, plastic, clay and gravel up to 5 feet thick, The Baltimore Sun reported in 2013.

The city Department of Transporta­tion said constructi­on was delayed nine months; it’s unclear why the project missed its deadline by more than a year and a half. In addition to the latent conditions, the department blamed the delay on “accommodat­ions to nearby businesses [and] other developmen­t in the corridor.”

The delay cost the city about $67,000, according to an agency spokesman, German Vigil.

“Delays always have implicatio­ns,” Pourciau said.

Pugh interrupte­d her transporta­tion director to emphasize that her administra­tion had been working diligently to complete the bridge.

“We have been in office since December 2016,” the mayor said. “We hired Michelle six months later. This has been moving forward. I said, ‘Let’s pay attention to this. Let’s get it done.’ And here we are, a year later, and it’s done. It really just takes focus.”

Young attributed the delay to obstacles in getting barges into place for constructi­on. Barges had to be used to build it in place of cranes, the council president said.

“If they were able to get the barge there, this bridge would have been done,” Young said. “It was delayed because they couldn’t get the barge where they really originally wanted to get it.

“With delays, costs go up. Are we happy with that? No. … I’m just happy where we are today.”