Transource Energy has been cleared to move ahead with the Maryland portion of a power line project, including a segment through northern Harford County, following the approval of a settlement agreement by state regulators this week.

The settlement order, issued Tuesday by the Maryland Public Service Commission, includes an alternativ­e route for the project’s eastern segment between Harford and York County, Pennsylvan­ia.

Transource wants to build 45 miles of new power lines for the Independen­ce Energy Connection project, which would improve the flow of power for PJM Interconne­ction, a regional transmissi­on organizati­on that manages a regional power grid serving 13 states. The new lines would create $800 million in savings for electric customers over 15 years, according to the project website.

“The Commission finds that this project will provide benefits to Maryland ratepayers, including enhanced reliabilit­y of electricit­y service and greater access to leastcost energy from elsewhere within PJM, while also accommodat­ing future developmen­t of renewable technologi­es such as offshore wind,” PSC Chairman Jason Stanek said in a statement.

The project, which initially called for building new power lines as well as new substation­s and upgrading existing stations, has one segment between eastern Maryland and Pennsylvan­ia and another between western Maryland and Pennsylvan­ia.

Transource, headquarte­red in Columbus, Ohio, is slated to build the 4.5-mile western section in Washington County; BGE will build the eastern section, spanning 6.6 miles, through northern Harford and a corner of northern Baltimore County along the utility’s infrastruc­ture and rights of way, according to the news release.

Many property and business owners on both sides of the Mason-Dixon Line, including farmers with land preserved for agricultur­al use, opposed the eastern portion when the proposed route between the Conastone substation in Norrisvill­e and a new Furnace Run substation in York County was unveiled a few years ago.

Harford County Executive Barry Glassman, the County Council, Harford’s legislativ­e delegation, even Maryland Gov. Larry Hogan, all expressed concern about the project, especially its potential impact on local agricultur­e. The County Council approved a resolution in 2018 stating its opposition to the IEC. Many local property owners pushed for Transource to use existing power line infrastruc­ture rather than build new lines and towers.

Transource has since submitted a plan with a revised eastern route, with the majority of the lines placed along existing BGE routes in Baltimore and Harford counties and PPL Electric Utilities lines in York County. The lines start at the Conastone substation just southwest of the intersecti­on of Route 23 and Route136, head west along BGE infrastruc­ture through the northeast corner of Baltimore County, then turn and head north into Pennsylvan­ia.

The lines go north along a PPL route, ending near the Otter Creek substation. New lines then head east from there, connecting with the new Furnace Run Substation and then another PPL route heading south, back down to the Graceton substation in Pylesville near Route 165. There also is an east-west line running between Graceton and Conastone, according to a map of the proposed alternate route on the Transource website.

Transource filed a petition for settlement, including the alternate route, with the Maryland PSC and the Pennsylvan­ia Public Utility Commission last October. The Harford County Council gave its unanimous approval to the settlement agreement in November.

The parties involved in the settlement include Transource, BGE, the Harford County government, landowner and community groups such as STOP Transource Maryland, PSC technical staff and the Power Plant Research Program, part of the Maryland Department of Natural Resources, according to the news release.

BGE and Transource must “minimize all constructi­on activities and additional constructi­on-related costs” that pertain to the Maryland segments of the project until Pennsylvan­ia regulators approve portions of the project in that state, plus PJM’s board must give its final approval, according to the release.

“The Glassman Administra­tion is pleased all parties have been able to come together to reach a settlement and one which maintains Harford’s protection­s of its agricultur­al land preservati­on easements,” county government spokespers­on Cindy Mumby said in an emailed statement Thursday.

Dan Rodricks is off this week. His column returns Wednesday, July 8.

 ?? TRANSOURCE ?? Transource has been cleared to move ahead with the Maryland portion of its Independen­ce Energy Connection power line project, including a part in northern Harford County.
TRANSOURCE Transource has been cleared to move ahead with the Maryland portion of its Independen­ce Energy Connection power line project, including a part in northern Harford County.

Newspapers in English

Newspapers from United States