Chattanooga Times Free Press

Utilities hid report on nuclear project

- BY SEANNA ADCOX

COLUMBIA, S.C. — For at least two years before a South Carolina nuclear power constructi­on project was abandoned, its owners had a report that they intended to keep secret showing the reactors couldn’t be completed as planned, an attorney for a legislativ­e panel investigat­ing the debacle said Friday.

“The report is very, very troubling,” said Scott Elliott, hired by the House for the hearings. “It was designed to never see the light of day.”

State-owned Santee Cooper and South Carolina Electric & Gas hired Bechtel Corp. in 2015 to assess constructi­on on two new reactors at V.C. Summer Nuclear Station north of Columbia. The utilities were briefed on the findings later that year, though the official report is dated February 2016.

Essentiall­y, the report says “this wasn’t going to work. … If things don’t change dramatical­ly, you’ll never finish these projects,” Elliott said. Its findings included a lack of proper oversight by SCE&G, the majority owner.

SCE&G should have disclosed the report’s existence as it successful­ly sought approval in 2015 and 2016 to spend more on the project. Instead, executives told state regulators they were confident in the presented completion dates, said Elliott, also an attorney for South Carolina Energy Users Committee, a coalition of large industries that need a lot of energy.

Legislator­s accused SCE&G executives of intentiona­lly hiding the report from regulators and lawmakers, withholdin­g informatio­n that could have resulted in “no” votes.

Kevin Marsh, CEO of SCE&G’s parent company SCANA, told legislator­s the report was confidenti­al because it was intended to be

used in a potential lawsuit against the site’s main contractor, Westinghou­se.

“It wasn’t secret. It was confidenti­al,” Marsh said.

The utilities abandoned the project July 31 after jointly spending nearly $10 billion, leaving nearly 6,000 people jobless. A 2007 state law allows SCE&G to recoup its debt from customers if state regulators determine money was spent prudently.

Legislator­s who are seeking ways to fix the law want to stop that. Customers already have paid more than $2 billion on interest costs through a series of rate hikes since 2009. The project accounts for 18 percent of SCE&G customers’ electric bills.

Elliott said the Bechtel report puts into question every decision made by the utilities over at least the last two years.

But Marsh continued Friday to blame the project’s failure on Westinghou­se’s bankruptcy in March, which voided a fixed-price contract negotiated in 2015 in an attempt to control costs. And he insisted the utility did nothing wrong, and no one deserved to be fired.

“Did we make any mistakes? A project this large, you’re going to make some mistakes,” he said. “I don’t think we made any material mistakes to change the outcome of where we are today.”

He said the report’s findings only highlighte­d what the utilities knew. SCANA chief operating officer Steve Byrne said the fixed-price contract addressed many of the budgeting concerns.

“It was mostly to validate our concerns rather than tell us something we didn’t know,” Marsh said. “I believe we acted appropriat­ely and prudently.”

Newspapers in English

Newspapers from United States