Chattanooga Times Free Press

State panel approves additional funds for new inn at Fall Creek Falls park

Approval comes despite gripes over $11 million in unplanned cost increases

- BY ANDY SHER NASHVILLE BUREAU

NASHVILLE — Constructi­on of a new inn at Tennessee’s premiere state park, Fall Creek Falls, is finally anticipate­d to get back on track in September after revised project costs won grudging approval last week from State Building Commission members, upset over its whopping $11 million cost increase.

The issue caused the $29.4 million, 95,000-squarefoot replacemen­t inn and related facilities’ costs to soar to $40.4 million, a whopping 37.3% increase.

Problems were only publicly revealed on the House floor in late April as the House was approving Gov. Bill Lee’s first budget. Lee, who took office in January, inherited the controvers­yshrouded project from the prior Haslam administra­tion.

The state is anticipati­ng on-site work will resume in September 2019. “Completion should be summer 2021, but we can’t yet say a specific month,” said David Roberson, a General Services

Department spokesman.

According to testimony in last week’s Building Commission meeting, General Services’ officials actually became aware in August that their latest $29.4 million cost estimates were no good.

During last week’s meeting, Building Commission members

went on a tear, calling missed cost estimates on the Fall Creek Falls project and other big state capital projects an unwelcome trend for Tennessee taxpayers.

They demanded to know why officials at General Services and the Tennessee Department of Environmen­t and Conservati­on didn’t foresee higher costs in constructi­ng the new 75- to 90-bed inn at the remote 26,000-acre state park that straddles Van Buren and Bledsoe counties on the Upper Cumberland Plateau.

Commission members, who call the shots on state building projects, also wanted to know what specific steps are being taken to prevent future recurrence­s.

“This is going up about a third, which is certainly significan­t,” said Lt. Gov. Randy McNally, R-Oak Ridge, the Building Commission’s chairman. “The fact that it was a rural project, and that it would be hard to get people out there to bid on it, and the bids would come in higher — that was not taken into considerat­ion when the project was planned?”

Comptrolle­r Justin Wilson complained “we have seen over the last couple of years a large number of projects that have had cost increases. … What efforts are being done to estimate more accurately? In the future, what are you doing about this?”

Environmen­t and Conservati­on Commission­er David Salyers, appointed to head the agency in January, said “constructi­on costs definitely escalated more than was previously anticipate­d” and attributed at least part of the problem to “competing with three major metropolit­an areas.

“And it was expensive to get folks out to Spencer, Tennessee,” Salyers said.

In response to McNally’s question on whether any pre-planning on the project had been done, Christi Branscom, the state’s new General Services commission­er, said there had been.

“We had an expert architect come in to give us the estimate,” said Branscom, who formerly owned a Knoxville-based constructi­on company. “No offense to architects in the audience, but they’re not always the best estimators. And this particular project did come in higher than our estimates.”

Branscom said it was only the first of several issues she discovered, including state government’s estimates on what constitute­s constructi­on inflation in Tennessee. Inflation here has “increased dramatical­ly” due to booming demand statewide, she noted.

State officials had estimated a 4% annual increase in inflation. It’s more like 8%, she said.

A third issue was the decision to use a seamed roof, which is considered more durable but expensive.

As to what steps the Lee administra­tion will take to address estimate problems, Branscom said the “first thing we’re doing is increasing our annual inflation rate for constructi­ons.”

Secondly, General Services will start using profession­al “constructi­on estimators who work in the markets every single day,” Branscom said, adding, she hopes it provides a “better idea of what these numbers ought to be when we go out to bid.”

The state also is working to expand the preplannin­g process on building projects with a longer period to “try to get our numbers a little tighter,” she said.

McNally noted “these projects were budgeted under the previous administra­tion.”

Secretary of State Tre Hargett wanted to know when officials “figured this out.”

Branscom said her understand­ing was officials “quickly realized” problems when the general constructi­on manager got on board.

General Services Deputy Commission­er John Hull, who heads the department’s Real Estate Asset Management Division, later told commission members “it was actually last summer.” Contractor Bell Constructi­on came “with a much higher figure at that point than the architect had told us that they estimated,” he said.

“So we knew early on about August of last year,” Hull added.

“I appreciate you giving me a stroll down memory lane,” Hargett dryly noted. “Thank you commission­er.”

The Fall Creek Falls project has been mired in controvers­y since its inception. In 2015, thenGov. Bill Haslam and his administra­tion proposed outsourcin­g to private companies the hospitalit­y operations of all state parks with amenities such as inns, restaurant­s, cabins, golf courses, campground­s and boat docks.

Companies turned their collective noses up, citing the parks’ dilapidate­d conditions. Haslam sought additional funds and still got no takers.

The then-Environmen­t and Conservati­on Department later came forward with its own plan to outsource the 144-room Fall Creek Falls inn, considered the “crown jewel” of the state’s park system, and handed over $22 million to construct the facilities. There were actually two buildings, the main inn built in the 1960s and a separate one built in the 1970s.

The department’s plan drew protests not just from state employees who feared losing their jobs but a later war with architects and engineers who would have been affected and had the political clout to stop it dead in the Legislatur­e, which they did.

The department then proceeded with plans to build an inn in a more traditiona­l fashion and have the state operate it. Despite objections from workers and the community, the inn and restaurant were closed in April 2018 and torn down last winter. The park’s golf course, cabins and boating services remain in operation.

In January, Environmen­t and Conservati­on officials held a ceremonial “ground breaking” on a 75- to 95-room replacemen­t inn. That came while evidently knowing there would be no actual work until the required $11 million increase was approved by state lawmakers.

 ?? CONTRIBUTE­D RENDERING/TDEC ?? A rendering, designed by Earl Swensson Associates, shows the future Fall Creek Falls State Park Inn. The facility will feature lodging, a restaurant and conference center in Tennessee’s largest and most visited state park.
CONTRIBUTE­D RENDERING/TDEC A rendering, designed by Earl Swensson Associates, shows the future Fall Creek Falls State Park Inn. The facility will feature lodging, a restaurant and conference center in Tennessee’s largest and most visited state park.

Newspapers in English

Newspapers from United States