Chattanooga Times Free Press

Fourth Street ramp to close for 2 months

TDOT says project should be complete by end of 2020

- BY BEN BENTON STAFF WRITER

A two-month-long closure of the U.S. Highway 27 North to West Fourth Street off-ramp starting this weekend will create some problems for drivers headed into downtown Chattanoog­a.

As work aims for completion by the end of the year on the $143.2 million U.S. 27 reconstruc­tion project that started in late 2015, northbound U.S. 27 motorists destined for the downtown area will have the choice of getting off at one of two remaining exits south of the Olgiati Bridge or one north of the bridge, according to Tennessee Department of Transporta­tion spokeswoma­n Jennifer Flynn.

Drivers headed downtown on Highway 27 North will have to take exits at Carter Street, M.L. King Boulevard or Manufactur­ers Road, on the north side of the Olgiati Bridge, to reach points downtown, according to TDOT.

“This closure will be in effect until mid-September 2020 and will allow the contractor access to the area needed to safely construct a new exit ramp,” Flynn said.

The project through downtown Chattanoog­a aims to widen and straighten the roadway’s original winding path and to improve onand off-ramps between the river and Interstate 24. Jackson, Tennessee-based Dement Constructi­on Co. is the contractor on the project.

Downtown Chattanoog­a dentist Dr. Frank “Bubba” Trundle Jr. has been plowing his way through the constructi­on project traffic to his office on Carter Street since the beginning, and the optimism he had for the project when he talked with the Times Free Press in 2016 has become frustratio­n and impatience, though he has a sense of humor about it.

“I think every time you figure out what to do, they change it on you,” Trundle said after braving the traffic Thursday afternoon.

“Thank goodness I don’t have to use the Fourth Street exit anymore, and I hope they open another exit where they can get on the freeway besides Fourth Street, because now they’re directing all the traffic down to M.L. King to get on,” he said.

“And get rid of those dad-blamed stop signs!” he said. “That’s the biggest pain that I’ve got right now, it’s these stop signs getting on the freeway with one lane and everybody diverting into two different entrance ramps to get on the darn freeway [at M.L. King].”

Like commuters, visitors headed north on Highway 27 for the Tennessee Aquarium, the Creative Discovery Museum or other attraction­s on the north end of the downtown area ordinarily would take the West Fourth Street exit.

Fortunatel­y, today’s motoring public is equipped with electronic devices and downtown destinatio­ns provide lots of informatio­n through social media, aquarium spokesman Thom Benson said Thursday.

“TDOT does a very good job of working with all of the stakeholde­rs in the Chattanoog­a area with updates on the constructi­on project, and any time there is something that’s going to cause a challenge for visitors, we try to use our communicat­ion channels to get that informatio­n to them,” Benson said.

“This project’s been ongoing for some time, so we’ve made some changes to our website to include alternate routes, such as coming up Broad Street,” Benson said. “But in addition to that, a lot of people these days are using Google Maps or other navigation tools like Waze that will let you know when there is a constructi­on zone or a closed exit, and it reroutes you automatica­lly.”

Some folks might still be caught off guard, but Benson said media coverage, TDOT updates and informatio­n posted on social media by downtown area businesses and attraction­s help keep downtown visitors up to date.

“In the past several months, the contractor has done two major traffic shifts on the project,” Flynn said of recent work. “On May 2, they shifted traffic to the final alignment on the mainline of U.S. 27 South. On June 19, they did the same thing on U.S. 27 North.”

Less than a week ago, the M.L. King Boulevard on-ramp was closed, creating an outbound workaround to get onto Highway 27, so motorists are seeing some new patterns as portions of the work are completed and others are begun. The detour is a simple left turn off of M.L. King Boulevard onto a new loop ramp that swings traffic up to the northbound lanes. That closure will remain in place until the new M.L. King Boulevard to Highway 27 North ramp is completed later this year, according to TDOT.

“Both of the recent ramp closures will help the contractor to be able to tie everything in from West M.L. King Boulevard to West Fourth Street,”

Flynn said. “This Saturday’s temporary closure of the off-ramp from U.S. 27 North to W. 4th Street is another piece in the larger puzzle that is the U.S. 27 project.”

Constructi­on on the project is now deep in its fourth year.

TDOT Region 2 director and assistant chief engineer Joe Deering announced in December that the project was behind schedule after problems arose when the contractor encountere­d “10 times more rock than estimated” during constructi­on of the project’s largest wall in the summer of 2018, TDOT officials said last year. There also were more undergroun­d voids discovered than were originally estimated, and new surprises lurked in other areas from old building and fill sites under the former roadbed.

The cost of the project also climbed sharply from its original $80 million price tag when the project started ramping up in 2011 and 2012 to $126 million as work started in late 2015. Over the course of the project, the cost has risen another $17 million. Funding to pay for the rising cost is borne by the state and federal government­s, officials said.

Work since December has flowed smoothly and the project is slated for completion by the end of the year with the project cost staying at $143.2 million, Flynn said Thursday.

Despite his frustratio­ns, Trundle said he has hope.

“That is the one thing that’s good about it; they’re running out of things to mess with us on,” Trundle laughed, remarking he was impressed with the crews’ ability to keep working while battling 2020’s record-setting rain.

“I think it’s going to be for the good,” he said, then hedged, “Call me in 2021 because, you know, 2020 is such a screwedup year, there’s no telling what could happen by the end of the year with that freeway.

“I’m not holding my breath on a finish in 2020. Nothing’s gone right yet in 2020,” he said. “But I am so ready.”

While constructi­on continues downtown and elsewhere, drivers can get the latest on constructi­on activity and livestream­ing SmartWay traffic cameras at TDOT’s traffic website, dial 511 from any land line or cellphone for travel informatio­n, or follow TDOT on Twitter for statewide travel or Chattanoog­a area-specific alerts.

 ?? STAFF PHOTO BY C.B. SCHMELTER ?? Traffic exits U.S. Highway 27 North toward Fourth Street on Thursday. Starting this weekend the ramp will be closed for two months to allow for reconstruc­tion.
STAFF PHOTO BY C.B. SCHMELTER Traffic exits U.S. Highway 27 North toward Fourth Street on Thursday. Starting this weekend the ramp will be closed for two months to allow for reconstruc­tion.
 ?? STAFF PHOTO BY C.B. SCHMELTER ?? Traffic exits U.S. Highway 27 North toward Fourth Street on Thursday.
STAFF PHOTO BY C.B. SCHMELTER Traffic exits U.S. Highway 27 North toward Fourth Street on Thursday.

Newspapers in English

Newspapers from United States