Chattanooga Times Free Press

I-24/South Broad headed for Aug. 31 finish

- BY BEN BENTON

$32 million project to reconstruc­t the interchang­es on Interstate 24 at South Broad and Market streets on Chattanoog­a’s Southside is on track for an Aug. 31 finish as crews work on the final phase of constructi­on and start repaving the interstate.

Crews on Friday were working on the frontage road, the project’s final phase in the constructi­on of a new 1.6-mile multilane road that runs parallel to I-24 from Broad to Market streets. Small teams were compacting the gravel roadbed as new traffic lights flashed at the road’s intersecti­ons with Williams and Market streets. At the end of the frontage road on Market Street, drivers headed to I-24 east will simply cross Market to take the existing on-ramp onto the interstate.

The project is 83.9% complete, Rae Ann Bradley, Tennessee Department of Transporta­tion spokeswoma­n, said.

Motorists traveling through the area will see a new surface being applied to I-24 this week.

“The contractor is scheduled to complete paving on I-24 in both directions between mile marker 177 and mile marker 180,” Bradley said in an emailed statement. “In addition, they’re scheduled to complete paving on the three U.S. 27 ramps — U.S. 27 north from I-24 east, U.S. 27 south to I-24 east and U.S. 27 south to I-24 west. All of this work will take place between 9 p.m. and 6 a.m. Tuesday night through Thursday night.”

The contractor, Charleston, Tennessee-based Wright Brothers Constructi­on, started the work in September 2020 and was dogged by supply chain issues in the summer of 2022, but Bradley said crews remained on schedule.

“The contractor should have everything finished, including the new frontage road from Broad Street to Market Street, by the scheduled completion date,” she said.

Bradley said there have been no significan­t changes in the cost of the project and no major problems.

When federal interstate­s were completed in the 1960s, the area of the current project was called the “big scramble” for its sprawling design, and the traffic count in the area in 1966 had increased from 37,000 to 51,000 vehicles per day, according to Chattanoog­a Times Free Press archives.

Now the traffic count in the same area ranges from about 71,000 per day west of the city to more than 118,000 vehicles per day between Missionary Ridge and the U.S. 27 interchang­e, according to 2022 state traffic data. Broad Street’s traffic count data from 2022 was around 23,000 vehicles a day.

The area around I-24 and South Broad has often been seen as the gateway to Chattanoog­a from the west, but the existing loops and ramps that served as exits and entrances were outdated, according to state officials.

The project aimed to improve the safety and operation of the interstate and accommodat­e current and future traffic demands, promote economic growth and support area redevelopm­ent.

State Sen. Todd Gardenhire, R-Chattanoog­a, one of the improvemen­t project’s biggest promoters, didn’t immediatel­y return phones calls or respond to emails seeking comment Tuesday on the project’s progress, but in the summer of 2022 he noted the project was hastened by booming developmen­t on the Southside, including a new stadium for the Chattanoog­a Lookouts.

On its Facebook page, Wright Brothers posted drone footage shot in February that showed much of the concrete work involved in constructi­on of the ramps and bridges connecting I-24 to the Southside.

As far as trucking bottleneck­s go, Chattanoog­a’s two heaviest-traveled interchang­es dropped in rank among the worst in the country.

In 2022, the intersecti­on of I-24/U.S. 27 was ranked at No. 29 on the American Transporta­tion Research Institute’s 100 worst freight bottleneck­s, but in 2023 it dropped to No. 39. Likewise, the Interstate 75/I-24 interchang­e known as the split dropped in the rankings to No. 59 in 2023 from No. 10 in 2022. The only Top 10 bottleneck in Tennessee is Nashville’s I-24/ Interstate 40 interchang­e at Interstate 440.

 ?? STAFF PHOTO BY OLIVIA ROSS ?? Work continues Friday at the interchang­e reconstruc­tion project at Interstate 24 and South Broad Street.
STAFF PHOTO BY OLIVIA ROSS Work continues Friday at the interchang­e reconstruc­tion project at Interstate 24 and South Broad Street.

Newspapers in English

Newspapers from United States