Will constructi­on of Jane Byrne Circle Interchang­e ever get done?

-

In uncertain times like these, some constants do remain: death, taxes and the seemingly never-ending reconstruc­tion of the Jane Byrne Circle Interchang­e.

It’s an embarrassm­ent that a project that was begun in 2013 and was supposed to be finished in 2018 won’t actually wrap up — if you even believe current projection­s — until late 2022. That’s nine years from start to finish.

Chicago built four major expressway­s — the Ryan, Eisenhower, Stevenson and Kennedy — in roughly the same length of time, from 1956 to 1964.

Also distressin­g: The reconstruc­tion’s original $535 million price tag has jumped to just shy of $800 million.

We have no gripe with the project itself. The former Circle Interchang­e — the concrete knot that ties together the Kennedy, Eisenhower and Ryan — was built in the 1950s and was never upgraded. Everybody in town agrees it was a mess.

The reconstruc­tion has been designed to increase the interchang­e’s capacity, bringing in additional car lanes, three new flyovers, and reconstruc­ted bridges over the expressway at Harrison, Monroe, Morgan, Taylor, Van Buren, Adams and Jackson streets.

The new interchang­e is a complicate­d piece of work, which accounts for some of the unexpected delays. And after constructi­on began, work crews discovered poorerthan-expected soil conditions. That meant that portions of the exchange, including massive retaining walls, had to be re-engineered to make them significan­tly stronger, which has driven up the price.

Given the project’s ambitious scope, the Illinois Department of Transporta­tion should have done better advance work to create a realistic budget and timetable. This smacks too much of the 2006 reconstruc­tion of the Ryan, originally priced at $550 million. Change orders hiked the price to nearly $1 billion.

There’s more work to come as part of the interchang­e project. The roadway and barrier walls on the northbound Dan Ryan, between Roosevelt Road and Madison Street, will be rebuilt, along with the Madison, Washington, Lake and Randolph exit ramps.

The southbound Ryan will include similar work, plus new undergroun­d stormwater tanks to help alleviate roadway flooding.

The project’s delays — and escalating costs — are another harsh reminder that undertakin­g ambitious road projects to solve traffic congestion is an increasing­ly expensive and time-consuming endeavor.

A better approach will always put a greater emphasis on mass transit.