Daily Local News (West Chester, PA)

Route 202 North lane, ramp closures set next weekend

- Staff Report

KING OF PRUSSIA » Lane and ramp closures will be in place next weekend on northbound U.S. 202 between the Boot Road and U.S. 30 interchang­es in East Whiteland and West Whiteland townships to complete a traffic shift on the northbound bridge over Amtrak, PennDOT said Friday.

From 10 p.m. Friday, Feb. 2, to 10 a.m. Saturday, Feb. 3, the right lane will be closed on northbound U.S. 202 approachin­g the work area as crews prepare to shift a single lane of northbound traffic onto the rebuilt inside half of the bridge Saturday morning. During the operation, a single lane of northbound traffic will travel through the work area using the northbound express lane that has been establishe­d on the southbound side of the expressway.

During the Express Lane traffic shift, northbound U.S. 202 motorists will not have access to the exit ramp to U.S. 30. The detour will direct northbound U.S. 202 motorists to continue to the Route 401 (Conestoga Road) Interchang­e and turn right onto Route 401 (Conestoga Road) to reach U.S. 30 (Lancaster Avenue).

Motorists are advised to allow extra time when traveling through the constructi­on area because slowdowns will occur. The work schedule is weather dependent.

The traffic shift marks the completion of the first stage of rehabilita­tion of the northbound bridge over the Amtrak rail lines at the southern end of the U.S. 202/U.S. 30 Interchang­e that began in March 2017. During that stage, crews rehabilita­ted the left side of the northbound structure, cleaning and refurbishi­ng the steel superstruc­ture and replacing the concrete deck and parapets.

Following the shift, crews will begin approximat­ely six months of work to remove the existing concrete deck and parapets; rehabilita­te the steel superstruc­ture; and redeck the outside half of the northbound bridge.

When work on the northbound bridge is completed in mid-2018, a new traffic pattern will be establishe­d in the work zone for rehabilita­tion of the southbound bridge. That new pattern will move two lanes of northbound traffic onto the northbound bridge and establish a single southbound express lane on the northbound structure.

One lane of southbound traffic will then be maintained on the southbound bridge while the southbound structure is rehabilita­ted and redecked a halfat-a-time.

PennDOT completed replacemen­t of the deteriorat­ed concrete pavement on the outer lane of the two-lane southbound U.S. 202 ramp to U.S. 30/Exton Bypass in December 2017. The concrete pave-

ment on the inner lane of the two-lane off-ramp will be replaced at night and on weekends under temporary work zone traffic patterns beginning in early spring. Those temporary patterns will be removed each morning by 5:00 AM to provide motorists twolanes on the ramp during peak travel times.

Deteriorat­ed concrete on the ramp from the eastbound U.S. 30/Exton Bypass to northbound U.S. 202 will be replaced beginning this spring.

The work is part of a

$26.4 million project to rehabilita­te the northbound and southbound U.S. 202 bridges over Amtrak and the adjacent U.S. 30 ramp, and to remove and replace deteriorat­ed concrete pavement on the U.S. 202 ramps to and from the U.S. 30/Exton Bypass.

Allan A Myers, Inc. of Worcester, Montgomery County, is the general contractor on the project which is financed with 100 percent federal funds.

For more informatio­n on this project, visit www. us202-300.com.

Newspapers in English

Newspapers from United States