El Dorado News-Times

A&P agrees to fund Rec Complex soccer fields

Concession­s plaza on back burner

- By Tia Lyons Staff Writer

An effort to build two new youth soccer fields at the El Dorado-Union County Recreation Complex can now move forward, thanks to a contributi­on from the El Dorado Advertisin­g and Promotion Commission.

On August 6, commission­ers committed $256,554 to complete the soccer fields.

The vote was unanimous among the five commission­ers who were present for a specially-called meeting to address the issue.

Commission­ers Sanjay Patel and Kelli Harrison were unable to attend the meeting.

For the past several weeks, complex board members have explored options to find additional resources to build soccer fields at the complex, which has eight fields that are designed for baseball and softball but have also been used for Pee Wee football and soccer practices.

The soccer fields are included in phase one of a plan to renovate and expand the complex.

The project is being covered by a $2.6 million commitment from the one-cent, El Dorado Works tax, which is earmarked for projects that spur economic developmen­t and improve municipal infrastruc­ture and quality of life in the community.

Phase one has largely been

completed.

The soccer fields and a new concession­s plaza, both of which will be built on the south end of the components, are pending.

Work has wrapped on the other components, including the completion of two existing youth baseball and softball fields and the constructi­on of two new youth fields on the south end of the complex and the installati­on of turf, lighting and fencing on four older fields on the north end of the facility.

The effort hit a snag several weeks ago after complex board members learned that engineerin­g fees would have to be paid from the $2.6 million budget.

Greg Harrison, chairman of the complex board, explained that fees for A.L. Franks Engineerin­g Inc., who is designing and overseeing the renovation project, were not figured into the budget because board members were initially told that the city has a profession­al services contract with the Texarkana-based firm.

Board members thought the contract would cover engineerin­g work that A.L. Franks is performing for the complex but after sorting out the matter, A.L. Franks explained that its contract is with the city and not the complex.

The city and Union County contribute to the annual operating budget for the complex. The complex sits just outside city limits on Champagnol­le Road and the city owns the land on which the facility sits.

On July 14, Jason Haley of A.L. Franks reported to El Dorado Works Board members that costs for constructi­on, engineerin­g and final inspection fees came to $2.09 million.

Two additional engineerin­g invoices came in following the report, leaving approximat­ely $400,000 in the project budget.

Bids for the soccer fields and concession­s plaza exceeded the budget balance and complex board members and city officials agreed that the soccer fields should be prioritize­d to help generate more revenue at the complex.

The A&P commission subsequent­ly stepped in to offer assistance.

‘Have that project completed’

Commission­ers Dianne Hammond, former vice-chairman of the complex board, and Paul Choate presented the funding request during the specially-called meeting August 6.

Hammond and Choate are also members of the El Dorado City Council.

“We have the soccer fields still pending and we lack $256,554 to have that completed. And that includes the lighting so what I would like to do is instead of them just doing the soccer fields without the lighting, go ahead and have that project completed,” Hammond said.

The addition of the soccer fields and improvemen­ts to the softball and baseball fields will help open up opportunit­ies for more and larger tournament­s, creating more income for the complex, she told A&P commission­ers.

Hammond also said the work includes parking lot improvemen­ts for the new fields.

Choate said an initial, base bid package of $671,824 had been narrowed down to a deductive bid of $581,000, which excludes parking lot improvemen­ts.

“The city is right on the cusp of starting our annual street maintenanc­e program and instead of buying gravel and spreading and packing, we’re going to be using the millage coming off city streets instead of buying gravel,” Choate explained.

Haley previously told the El Dorado Works Board that Entergy was calculatin­g costs for electrical work that will need to be completed to make way for the soccer fields.

Choate explained a $5,000 line item has since been plugged into the project budget to connect three-phase electrical components.

“There will be backup electrical plug-ins for food trucks or whatever and the lighting itself was included in that initial bid,” Choate said.

A&P Chairman Barry Bagwell pointed to past issues with replacemen­t lighting and Hammond and Choate said the project includes LED lighting, which will save on energy costs.

Hammond also said the complex charges a fee for the use of the fields for late practices and other athletic activities that go on after dark at the complex.

Commission­er Alan Meadows asked who handles routine maintenanc­e and repairs for the complex.

Hammond said the complex manager, the Boys and Girls Club of El Dorado, is responsibl­e for the duties and the Department of Public Works provides assistance.

Milam Constructi­on submitted the low bid of $343,989 for the concession­s plaza and complex board members said they would seek additional funding for the project later.

Phase two of the master plan for the complex calls for a baseball field that could be by older teens and adults, possibly to host college games.

Major parking lot improvemen­ts are also planned for the second phase.

Newspapers in English

Newspapers from United States