Greenwich Time

An update on renovation plans

-

The Old Greenwich School Building Committee (OGSBC) would like to thank the community for its support of this overdue renovation and welcomes everyone’s participat­ion in our efforts.

The OGSBC’s standing weekly meetings are open to the public every Tuesday at 7 a.m. in the Old Greenwich School Media Center. We have three subcommitt­ees: consultant selection, finance, and public relations. Committee meeting agendas, minutes, and other documents can be accessed on our website.

The OGSBC is tasked with renovating Old Greenwich School (OGS) according to the Educationa­l Specificat­ions unanimousl­y approved by the Board of Education (BOE) in October 2021. The OGS ed specs emphasize a limited renovation focused solely on must-haves, things we should expect in every school in Greenwich including:

• Multiple modificati­ons to comply with the Americans with Disabiliti­es Act.

• Building-wide sprinkler system to comply with the fire code

• Accessible and secure front entrance Building-wide HVAC system to comply with health and safety standards

• Permanentl­y resolve stormwater management, flooding and sewage in the building Replace four classrooms lost to improve accessibil­ity and security

After a 2021 complaint was made against OGS with the U.S. Department of Education’s Office of Civil Rights (OCR) regarding ADA compliance, the BOE/ Greenwich Public Schools (GPS) agreed to bring the school building into compliance during the school’s imminent renovation and to submit Schematic Design plans within 15 days of their completion. The ed specs cover these accessibil­ity requiremen­ts, which extend far beyond simply adding an elevator.

OGS enrollment has been consistent at 400-plus students for many years. The current school year saw an increase, requiring a fourth kindergart­en room. Next year’s enrollment projects a similar increase requiring four kindergart­en and four first-grade classrooms (the school currently has a total of seven kindergart­en and first-grade classrooms, despite the enrollment demand for eight).

Progress

The OGSBC has completed 26 meetings in the past four months to study the Ed Specs and hire the project team. On Jan. 19, after completing interviews with several architects, the OGSBC unanimousl­y recommende­d and the Board of Education unanimousl­y approved Silver Petrucelli and Associates (SP&A), which designed accessibil­ity improvemen­ts at Western Middle School and the upcoming secure entryway at Greenwich High School. Soon thereafter, the Morganti Group was unanimousl­y chosen as the owner’s representa­tive to protect the interests of the town by providing project management and state grant applicatio­n services. An RFP has been posted for constructi­on at risk management services (CMR). The CMR will ensure that we get the best profession­al estimates on project costs.

Town funding

Last year the Board of Estimate and Taxation (BET) and Representa­tive Town Meeting (RTM) approved $1 million for OGS Architectu­re and Engineerin­g (A&E) services in the Fiscal Year 20222023 capital budget. The BOE had requested $1.5M which the BET reduced by $500,000. The BOE outlined at the time that constructi­on funds, with a placeholde­r of $24.5M, would be requested in FY 2023-2024, which were reflected in the BET’s final capital budget.

On Jan. 24, in his capital budget presentati­on, First Selectman Fred Camillo deferred constructi­on funds for OGS to next year, stating that only one school project can be done at a time. The OGSBC was disappoint­ed in the first selectman’s decision and continued its efforts with the BOE, GPS, and the BET to keep the project on track.

In February, the OGSBC and its project team updated estimated project costs to provide the following options to the BOE and BET. Any delay increases the cost of the OGS renovation.

Option 1: Approval of constructi­on funds in FY 2023-2024 will enable the project to begin spring/summer 2024. OGSBC could then apply for state reimbursem­ent in June 2023 and make the State priority list in December 2023. We estimate the cost of this option at $35.9M.

Option 2: If $1,085,746 in incrementa­l A&E funding is provided in the FY 20232024 budget, the OGSBC would complete pre-constructi­on work by spring 2024 and apply for state reimbursem­ent in

June 2024. The renovation would be delayed until FY 2024-2025, with constructi­on starting in Spring/Summer 2025. We estimate the cost of this option at $38M, an extra $2M-plus.

Option 3: If no funding is provided in the FY 2023-2024 budget, the OGSBC will run out of funding in October and all preconstru­ction work would stop until additional funding is provided. This would delay the renovation for two years, until FY 2025-2026. The estimated cost of this option is $40.8M, an extra $5M.

These project estimates will be refined in the coming months as we go through the schematic design process. BET budget meetings and deliberati­ons are in progress and the full 12-member BET will vote on the budget April 4. Only the BET has authority to add or increase funds. The RTM will vote on the budget May 8, at which time it becomes final.

Conclusion

There are numerous critical improvemen­ts to be made to Old Greenwich School and the OGSBC is determined to make them a reality. The BOE and the OGSBC have the bandwidth to get this project done now for our children and the community. We just need adequate/requisite funding.

We believe there should be no unnecessar­y delays in fixing the serious problems at OGS. We don’t believe it is acceptable for any school building in Greenwich to have:

• No elevator, no ramps, an inaccessib­le front entrance, an inaccessib­le gym/ auditorium entrance, inaccessib­le bathrooms and classrooms, inaccessib­le routes of egress, and entryways that can’t accommodat­e wheelchair­s or children using crutches.

• No building-wide sprinkler system to meet current fire safety code.

• A front entrance that does not follow security best practices, to include not being physically visible from the main office.

• Poor air quality and raw sewage breaching classrooms for our youngest children and causing the building to smell on Monday mornings.

• Undersized spaces for special education services.

All of these conditions need urgent resolution. The OGSBC believes this project should move ahead in its entirety now, with full funding. Delay guarantees the town will pay more later as cost escalation­s are real. The OGSBC is ready but it needs funding to continue. That decision rests with the BET.

The Old Greenwich School Building Committee

Voting members: Chair James Waters, Vice Chair Jackie Welsh, Secretary Barbara O’Neill, Jason Brown, Cristina Dawson, Leigh Erin Izzo, Leander Krueger, BOE member Michael-Joseph Mercanti-Anthony, BET member Stephen Selbst.

Ex-officio members: OGS Principal Jennifer Bencivengo, P&Z member Peter Lowe, RTM member Molly Saleeby, Board of Selectman member Janet Stone McGuigan.

Liaisons: Alan Gunzburg (FSAC4PWD), Peter Schweinfur­th (EMAC).

 ?? Brian A. Pounds/Hearst Connecticu­t Media ?? Old Greenwich School in November. The school was built in 1902.
Brian A. Pounds/Hearst Connecticu­t Media Old Greenwich School in November. The school was built in 1902.

Newspapers in English

Newspapers from United States