Houston Chronicle Sunday

End in sight for U.S. 290 project

Widened main lanes — all 38 miles — will open by end of 2018

- By Dug Begley

Frequent drivers on U.S. 290 recall two different eras: Before Constructi­on and During Constructi­on.

Before miles of constructi­on started in 2011, the northwest Houston freeway was a tied-up mess, slowed to a crawl by increased demand. During is six years of closures, lane changes and narrow stretches shared by heavy trucks — along with even more traffic.

“It’s been like having a root canal for six years,” said Peter Perez, 42, who commutes from Jersey Village to his office in Uptown.

Texas Department of Transporta­tion officials said the end is near. Really.

Most major constructi­on along the main lanes of U.S. 290 will end in 2018. Every new wide lane open. Every bridge built. Eleven lanes, including a reversible HOV lane, from Loop 610 to Texas 6, and nine lanes from Texas 6 to Waller County. All open by the end of 2018.

“They are going to see stuff open up if we can do it safely,” said Frank Leong, area engineer for TxDOT’s West Harris County office. “The bridges are controllin­g the schedule right now.”

The last segments to start constructi­on, west of the Grand Parkway, will be the first to open under TxDOT’s current plans. Leong said that stretch, the easiest to build because it required the fewest bridges and fewest utility relocation­s, likely will open in March or April.

About six months later, if schedules proceed as anticipate­d, the freeway should be fully open from Loop 610 to the Sam Houston Tollway — including the lengthy work to rebuild all the connection­s to and from Loop 610, Interstate 10 and frontage road entrances and exits.

Officials said work will speed ahead and the project will be in

finishing touches phase by the time Houstonian­s ring in 2019.

“Things are looking very good that we are going to beat that,” Leong said, “but we’ll stick to the schedule we have now.”

The final portions likely will be around FM 1960 and Eldridge, he said, where the bridges and frontage roads will be some of the last built.

After years of exasperati­on and nerve-wracking and emotionall­y draining drives down U.S. 290, many commuters were dulled by the news the end is nearing.

“It’s encouragin­g to see it all come together,” said Melanie Gerber, 46. “But until I see it open, I won’t celebrate.”

Broken into 13 projects, widening the 38 miles of U.S. 290 from Waller County to Loop 610 is the largest ongoing freeway rebuild in the region, and, many drivers say, the most needed. Officials expect the population along the corridor to roughly double from 2010 to 2035 to about 1 million people.

Currently, about 215,000 vehicles travel the freeway east and west of the Sam Houston Tollway each weekday.

To accelerate constructi­on, TxDOT teamed with the Harris County Toll Road Authority, which offered $400 million for the $1.8 billion project for three managed lanes down the center of the freeway. Officials hailed the deal as a way to deliver needed freeway expansion sooner rather than later.

Then the deal deteriorat­ed as toll officials — chiefly county leaders — and TxDOT could not agree on specifics of how the managed lanes and freeway would interact. To separate the parties, HCTRA agreed to contribute $200 million — half the original offer — and cede control of the Katy Managed Lanes to TxDOT. The state then decided to build only a single, reversible HOV lane and instead have a fifth general use lane in each direction from Loop 610 to Texas 6.

The revised deal, announced in 2014, still is being finalized, as state and county lawyers devise language to allow the transfer of the I-10 managed lanes to TxDOT control.

Meanwhile, work on the project slowed or stalled for a variety of reasons, notably monthslong delays in relocating utilities — often outside the control of state officials and the project’s contractor­s — and heavy rains in 2015 and 2016.

One section of the project, from Pinemont to West Little York, had to be handed over to another builder after the original contractor defaulted on all of its projects in Texas when the company collapsed.

The various hiccups, major and minor, changed anticipate­d opening times by months or years. At the end of 2015, TxDOT said work remained on pace to open by the end of 2017. By late 2016, they were predicting everything would be finished by the end of 2018.

Officials are much more confident of openings as they proceed, because they are literally and figurative­ly on solid ground, with miles of concrete poured and steel rebar laid. Though a lot of dirt remains to be moved, most efforts to finish the job rest on manpower building the lanes and concrete dividers.

Crews also are close to opening a major component of the Loop 610 interchang­e, which will reconnect the HOV lane. The work also coincides with openings planned in January for some of the frontage road access.

“This job is going to open up a lot of things next month,” said Hamoon Bahrami, project engineer for the U.S. 290 project.

The openings also allow work to concentrat­e in the center of the interchang­e, where one of the last steps will be returning the connection from northbound Loop 610 to westbound U.S. 290 to the interior of the interchang­e. Of the major connection­s between U.S. 290, Loop 610 and I-10, it is the last piece.

The final few months, however, will not be pain-free. In some spots, crews still are hanging beams for some overpasses, which will lead to highway closings and detours. Lanes will remain narrowed in spots for months to come.

Work at FM 1960, meanwhile, will stretch into 2019, but not on the freeway itself, Leong said.

TxDOT still is considerin­g a plan to allow off-peak HOV use of the adjacent lane to the reversible lane, traveling the opposite direction.

The proposal, preferred by Metropolit­an Transit Authority, would use the innermost lane of westbound U.S. 290 as a transit and carpool lane in the mornings, and then the fast lane of eastbound U.S. 290 in the evenings. The lane would act as a compliment to the reversible HOV lane, but be open to all drivers outside certain peak commuting times.

Leong said the proposal requires TxDOT to hold public hearings as it is a change to the approved plan. The hearings would occur sometime next year, Leong said.

If approved, the change only requires the installati­on of signs and additional road markings.

 ?? Will Thorne photos ?? Workers remove a form from a new sign post during constructi­on on Highway 290. Constructi­on to widen the northwest freeway from Loop 610 to Waller County began in 2011. Officials say finishing touches will be complete by the time Houstonian­s ring in...
Will Thorne photos Workers remove a form from a new sign post during constructi­on on Highway 290. Constructi­on to widen the northwest freeway from Loop 610 to Waller County began in 2011. Officials say finishing touches will be complete by the time Houstonian­s ring in...
 ?? Will Thorne ?? TxDot teamed with the Harris County Toll Road Authority on the U.S. 290 project, which is estimated to cost $1.8 billion.
Will Thorne TxDot teamed with the Harris County Toll Road Authority on the U.S. 290 project, which is estimated to cost $1.8 billion.

Newspapers in English

Newspapers from United States