Spur 5 faces long closure, creating traffic headache

- By Dug Begley

Relieving one of Houston’s worst bottleneck­s will come with some lengthy complicati­ons for northbound drivers on Interstate 45 headed into Houston’s central business district, starting Friday night.

After years of delay, work is starting on a modificati­on to Spur 5, the ramp that connects northbound I-45 traffic to downtown via Pease and St. Joseph. The spur is being rebuilt to also be the connection from northbound I-45 to Interstate 69, also U.S. 59 in the Houston area.

Though it is a major improvemen­t, the work means seven months of constructi­on detours for downtown-bound drivers, according to the Texas Department of Transporta­tion. Crews will close Spur 5 at Scott Street starting at 9 p.m. Friday, so they can demolish the ramp parallel to I-45.

In the interim, drivers who would normally use

the spur will exit at Scott and use the I-45 frontage road to travel into downtown. More than 13,000 vehicles use Spur 5 to access downtown at St. Joseph, according to a 2015 TxDOT traffic count. More than 200,000 vehicles use I-45 in the area.

In addition to affecting downtown-bound traffic, the spur closure means drivers won’t be able to access northbound I-45 at Scott Street, said Deidrea George, spokeswoma­n for TxDOT in Houston.

Officials with Houston Public Works and the Houston Downtown Management District are working with TxDOT to reach out to drivers and businesses.

Public works is also “currently evaluating the signal timing along the corridor to see if modificati­ons are necessary,” said deputy public works director Jeff Weatherfor­d.

Improvemen­t predicted

When finished in mid2019, the new interchang­e will be a marked improvemen­t, said Quincy Allen, district director for TxDOT in Houston. It will reduce sudden weaving where the freeways cross.

“Changing that is a major improvemen­t,” Allen said. “Not only does it help take away a lot of that (congestion), but it is a much safer interchang­e.”

The new interchang­e also eliminates the ramp that now connects the fast lane of northbound I-45 to southbound I-69.

Typically, modern highway design favors all exits and interchang­e ramps to be on the right side of the freeway where traffic is intended to move slower.

Having the ramps on both sides of northbound I-45 and so close to the interchang­e led to problems with through-traffic jammed as drivers darted between the lanes. Pulling the I-69 ramps back and using Spur 5, officials said, will mean less weaving. The ramp from eastbound U.S. 290 to Interstate 10, opened in late 2014, was designed for the same purpose and many drivers say it has improved traffic flow along U.S. 290 despite many delays related to the ongoing freeway constructi­on.

Work on Spur 5, meanwhile, faced delays of its own moving toward constructi­on. Largely designed by 2009, the project sat awaiting funding for roughly five years as TxDOT spent money elsewhere.

Once the money was secure, the project languished as Tradeco, the Woodlands-based contractor for the job, struggled to keep all of its Texas highway projects going. Tradeco eventually defaulted on all its highway jobs in mid-2015, leaving TxDOT and the surety bond company that insured Tradeco to regroup.

TxDOT rebid the job in January, awarding it to Williams Brothers Constructi­on, one of the largest road builders in the area. The company’s $30.5 million bid was roughly $2 million more than Tradeco estimated in 2014.

Allen said last month that the bid includes incentives for Williams Brothers to finish the southbound ramp quickly and reopen Spur 5’s connection to downtown. The company can make up to $520,000 for successful­ly speeding up the work.

Delays within the company’s control, however, could cost the Williams Brothers, Allen said, which is a common feature of TxDOT contracts.

The interchang­e work is hardly the end of constructi­on along the I-45 corridor around downtown, with many considerin­g it a precursor to potentiall­y a decade of constant constructi­on. TxDOT is proceeding with plans to realign I-45, I-69 and the interchang­e with Texas 288 as part of a $3 billion redesign of the downtown freeway network.

Major work in 2020

The first of seven projects to rebuild interchang­es, widen the freeways and shift I-45 to run parallel to I-69 along the east side of downtown is scheduled to begin in 2020, about a year after the Spur 5 work is set to finish.

Allen said the Spur 5 project is being designed with the future interchang­es in mind, but will require some minor modificati­ons once I-45 moves.

He said officials are also working to address concerns about bicycle and pedestrian safety where the new entrance at Scott will connect to Spur 5. Riders have raised concerns, noting Scott is a major entry point to the University of Houston and numerous cyclists are expected to use the intersecti­on.

 ?? Yi-Chin Lee / Houston Chronicle ?? Spur 5, which runs parallel to Interstate 45 near the University of Houston, will shut for seven months starting Friday at Scott, so a new ramp can be built.
Yi-Chin Lee / Houston Chronicle Spur 5, which runs parallel to Interstate 45 near the University of Houston, will shut for seven months starting Friday at Scott, so a new ramp can be built.