Judge says IBM owes Indiana millions
INDIANAPOLIS — IBM owes Indiana $78 million in damages stemming from the company’s failed effort to automate much of the state’s welfare services, a judge has ruled in a longrunning dispute.
Marion Superior Court Judge Heather Welch issued the ruling dated Friday, nearly six months after she heard arguments from attorneys for the state and IBM Corp.
The Indiana Supreme Court ruled last year that IBM had breached its contract, and it directed the trial court to calculate the damages.
Armonk, N.Y.-based IBM said Monday it will appeal the decision.
$1.3 billion contract
Indiana and IBM sued each other in 2010 after then-Gov. Mitch Daniels, a Republican, canceled the $1.3 billion contract that his administration reached with the company to privatize and automate the processing of Indiana’s welfare applications.
Under the deal, an IBM-led team of vendors worked to process applications for food stamps, Medicaid and other benefits.
Residents could apply for the benefits through call centers, the internet and fax machines. The contract was pulled in late 2009, less than three years into the 10-year deal, following complaints about long wait times, lost documents and improper rejections.
The state sought more than $172 million from IBM, but the judge ruled IBM responsible for $128 million in damages. That amount was offset by about $50 million in state fees that the company was owed.
IBM criticizes ruling
IBM said in an email statement that it believes the judge’s ruling “is contradicted by the facts and the law.”
“IBM worked diligently and invested significant resources in its partnership” with the state to help turn around “a welfare system described at the time by Indiana’s governor as one of the worst in the nation,” the company said.
Welch heard arguments from both sides on Feb. 10. She was scheduled to rule by early May in the complicated case, but lawyers twice agreed to allow the court more time.
Indiana initially sued IBM for the $437 million it had paid the company by the time the contract was pulled — a figure that was reduced before trial to about $170 million. IBM countersued for about $100 million that it said it was owed.
Welch wrote in her ruling that the bulk of what IBM owes the state stemmed from renegotiated deals with subcontractors to fixed payment amounts rather than the incentive-based payments they received from IBM. Welch said those new deals addressed “shortcomings” that led to the problems under IBM.
Needy families
Peter Rusthoven, one of the state’s private attorneys, said IBM’s failures hurt needy Indiana families.
“This has been a long, tough battle with a big corporation that refused all along to take responsibility for its poor performance,” he said.