Houston Chronicle

ERCOT, clean energy developers clash

State’s grid operator warns of a possible ‘catastroph­ic failure’

- By Claire Hao STAFF WRITER

Flaws in some solar, wind and battery storage resources on the Texas power grid could lead to issues that could cause “immediate catastroph­ic grid failure” if they are not addressed, the Electric Reliabilit­y Council of Texas said.

ERCOT, the state’s power grid operator, and owners of clean energy resources haven’t been able to reach consensus on what to do about the problem despite months of negotiatio­n. An industry proposal was tabled by ERCOT’s board Tuesday to allow both sides to address ERCOT staff’s concerns, despite protest from developers that its proposals and continued regulatory uncertaint­y with the delay could chill investment in Texas.

“Retroactiv­e implementa­tions of any market rules without any technical or commercial­ly feasible path to compliance sends a very clear signal and chilling effect to any additional investment,” Omar Martino, executive vice president of markets and regulatory for energy developer Invenergy, said at an April ERCOT subcommitt­ee meeting on the issue.

Clean energy resources have grown rapidly on the Texas grid in recent years as technology costs have come down and federal incentives have infused billions of dollars into the industry, making them competitiv­e with traditiona­l fossil fuel power plants. They’ve been credited with lowering electricit­y costs, providing the grid with needed supply and helping decarboniz­e electricit­y production, the second-largest source of climatewar­ming emissions nationally.

As renewable energy makes up a greater share of the grid, ERCOT said it has posed new challenges too, such as power availabili­ty that depends more on weather conditions. Clean energy developers, meanwhile, have accused ERCOT of discrimina­tory policy before, most recently for utility-scale battery storage.

The latest debate centers around a device required by wind, solar and battery resources called an inverter. This device converts the direct-current power these resources produce to alternatin­g-current, the electricit­y that comes out of a wall outlet.

When there is a voltage or frequency disturbanc­e on the grid, caused by lightning strikes or equipment failures, ERCOT expects power generators to “ride through” the disturbanc­es and continue producing power. But inverter-based resources such as wind, solar and batteries — especially the oldest ones — may sometimes not be able to ride through the disturbanc­e and could “trip” offline and disconnect from the grid. This could lead to a domino effect of other generators tripping offline, which could in a worst-case scenario result in the “rapid collapse of part of or all the ERCOT system,” according to ERCOT.

ERCOT has experience­d a growing number of these inverter-based resource failures, particular­ly in West Texas. In 2021 and again in 2022, more than 1,000 megawatts of solar resources tripped offline near Odessa, prompting the North American Electric Reliabilit­y Corp. (NERC), an internatio­nal regulatory authority, to recommend ERCOT rectify the risk.

“What’s a future problem for most of the world is an existing problem, a current problem in ERCOT,” said Dan Woodfin, its vice president of system operations, at the April subcommitt­ee meeting.

Both ERCOT and clean energy developers agree on the need to address the problem. What they disagree on is the scope to which hardware and software upgrades should be required.

ERCOT wants to impose ride-through guidance from the Institute of Electrical and Electronic­s Engineers, an internatio­nal standards associatio­n, on wind, solar and battery storage resources that have signed an agreement to connect to the grid by June 2023. Developers argue that the effective date for the new requiremen­ts should be June 2024, or after the Public Utility Commission of Texas, the state utility regulator, approves them.

ERCOT is concerned that 20 to 30 gigawatts of resources would be exempted from the new requiremen­ts with a June 2024 effective date, leaving too much risk. Developers argue that retroactiv­e requiremen­ts would jeopardize already-approved financing and constructi­on plans. Developers say these newest resources pose minimal risk to the grid and that verificati­on standards for the new IEEE guidelines are still in developmen­t.

Existing resources on the grid, meanwhile, would have to be evaluated to ensure they comply with current ridethroug­h requiremen­ts; if not, developers would need to implement upgrades to remedy the flaws. Both sides have agreed that all software upgrades are commercial­ly reasonable.

Ryan Quint, a former NERC engineer who was the primary author on nearly all of the organizati­on’s reports on the issue, is now a consultant working with Clearway Energy, one of the developers. In comments to ERCOT, Quint wrote that nearly 90% of the resources can address their issues with commercial­ly reasonable fixes such as software upgrades, including the vast majority of solar issues in both of the Odessa events.

Disagreeme­nts remain on hardware upgrades, which developers say could cost millions for the oldest resources on the grid, potentiall­y forcing developers to retire these assets early instead of make uneconomic investment­s. Clean energy developers have outlined a process to apply for exemptions, rather than exemptions granted at ERCOT’s discretion. ERCOT staff, however, are wary.

“My question is, what is the point of a standard when anytime you fail it, you can ask for an exemption to set a lower standard going forward? That doesn’t seem to make sense,” ERCOT’s Woodfin said at the April subcommitt­ee meeting.

The rule, known as Nodal Operating Guide Revision Request 245, will be revised in ERCOT’s Technical Advisory Committee before it is brought back to the ERCOT board for a vote. It then goes to the PUCT for ultimate approval.

 ?? Jon Shapley/Staff photograph­er ?? A battery storage yard is shown at the Blue Jay solar and storage plant in Iola. ERCOT and clean energy developers disagree on how to remedy flaws in some resources that could lead to “immediate catastroph­ic grid failure.”
Jon Shapley/Staff photograph­er A battery storage yard is shown at the Blue Jay solar and storage plant in Iola. ERCOT and clean energy developers disagree on how to remedy flaws in some resources that could lead to “immediate catastroph­ic grid failure.”

Newspapers in English

Newspapers from United States