Imperial Valley Press

LaBrucheri­e project is the culminatio­n of years of work

- STAFF REPORT

EL CENTRO — About 45 days into an ambitious constructi­on job to expand LaBrucheri­e Avenue from two lanes to four, resident Phil Moran said he couldn’t be happier with the way the city is handling the project.

“They’re doing a pretty good job of keeping the dust down, keeping the area clean, and keeping it all accessible,” he said Monday.

Accessibil­ity is key for Moran; he lives and operates his licensed contractin­g business in the blast pattern of the work zone, around 200 yards to the west of LaBrucheri­e Avenue, on the corner of Olive Avenue and 21st Street.

Moran said he’ll deal with traffic delays, even if they last another six to eight months, for the relief that will come from an expanded roadway. “When school is in, and as narrow as it’s been, there can be 15 to 20 cars deep at the intersecti­on,” he said of conditions before constructi­on got under way.

“I think it’s all good. I’m happy to see it,” Moran added of the work.

Imperial Irrigation District and AT&T vans and trucks could be seen in the area Monday, as workers with both utility companies continued to move power lines and network cables in the area, said Abraham Campos, director of the El Centro Public Works Department.

City officials are likely hoping all residents are as understand­ing as Moran, considerin­g the LaBrucheri­e project, which started Aug. 27, isn’t projected to be finished until March 30, 2019.

“We’ve been in very close communicat­ion with residents fronting the properties (along LaBrucheri­e). We’re thankful to them . ... It’s going to better when it’s done. We’re all looking forward to this new and improved way of traveling through LaBrucheri­e Avenue,” Campos said Monday.

Mayor Cheryl Viegas Walker seconded that sentiment. “The project has been a long time coming; probably one of the segments of roadway the city has had the most complaints from residents about because it is so heavily traveled.

“Because we’re now able to expand it to the four lanes that it is planned for, it’s going to greatly enhance mobility in that area, whether you’re traveling from Imperial, El Centro or Calexico,” Walker continued.

Campos described the project as being in the thick of Phase 1, which looks to move utilities, rebuild the single-lane road into two lanes and install curbs, gutters and sidewalks on the western side of LaBrucheri­e from Orange Avenue to the south, to Barbara Worth Drive to the north.

Around the end of 2018 or first of 2019, constructi­on will change sides, as Phase 2 moves forward in rebuilding and expanding the east side of the avenue, Campos said.

He said IID, the Gas Co. of Southern California, Spectrum and AT&T, as well as the El Centro Elementary School District have all been working well together and in close coordinati­on to make sure the project goes over without any major hitches and that all project timelines are met. Granite Constructi­on won the constructi­on contract and Dynamic Consultant Engineers is managing constructi­on, Campos added.

When all is said and done, the project will have cost around $4.5 million, Campos said, between constructi­on, engineerin­g and acquiring property on LaBrucheri­e Avenue.

Constructi­on alone cost the city $3.2 million, which was paid for largely paid for through voter-approved Measure D half-cent sales tax monies by way of the Imperial Valley Local Transporta­tion Authority, Walker and Campos said. Campos added that about $255,000 of the project cost came from the state gas tax, which voters will be asked whether to repeal in the November election.

Widening LaBrucheri­e Road has been on the city’s wish list for a long time, but issues of eminent domain delayed the project for about two years, Campos and Walker said.

“What you’re seeing out there is basically the culminatio­n of about five years of work,” Campos said.

The city had to acquire two properties along LaBrucheri­e in order to make the expansion happen. Walker said using eminent domain was a costly process that required the project be fully funded from the start. “Having all of those pieces in place, it did take a significan­t period of time,” she said.

“But it’s going to be worth the wait,” the mayor added.

Eminent domain is a government’s, or its agent’s, right to expropriat­e private property for public use, with payment of compensati­on.

Moran may be pleased with the project, but Campos understand­s there might be more than a few morning and afternoon travelers cursing the project as traffic delays dot the area. “Sometimes citizens ask about constructi­on and it causes questions,” he said, “but it’s a necessary evil till we get to a better place.”

Still, Moran did joke that while this isn’t the city’s problem, if he’s learned anything from the LaBrucheri­e project, it’s that local drivers don’t know how to use four-way stops.

With the traffic signal at the corner of LaBrucheri­e and Main Street offline during constructi­on, the intersecti­on is back to good ol’ stop signs.

“The aggravatin­g thing for me are all the ding dongs out there who can’t use a four-way stop,” Moran said.

 ?? PHOTO IMPERIAL VALLEY PRESS ?? Signs directing traffic can be seen throughout LaBrucheri­e Avenue between Orange Avenue and Barbara Worth Drive as the city is 45 days into an eightmonth project to expand LaBrucheri­e from two lanes to four lanes. On Monday, constructi­on crews were on site to continue the work and local utilities were moving power lines and other cables.
PHOTO IMPERIAL VALLEY PRESS Signs directing traffic can be seen throughout LaBrucheri­e Avenue between Orange Avenue and Barbara Worth Drive as the city is 45 days into an eightmonth project to expand LaBrucheri­e from two lanes to four lanes. On Monday, constructi­on crews were on site to continue the work and local utilities were moving power lines and other cables.

Newspapers in English

Newspapers from United States