Inland Valley Daily Bulletin

Boeing steps up inspection­s on 737 Max after door blew out in flight

The company also will bring in outside parties to review its quality controls and suggest improvemen­ts

- By Anthony Palazzo and Ryan Beene

Boeing Co. will step up inspection­s of aircraft during production and open its factories to airline customers as it seeks to improve quality and bolster confidence in its 737 Max following a neardisast­er on an Alaska Airlines flight this month.

A Boeing team has been sent to its biggest supplier, Spirit Aerosystem­s Holdings Inc., to inspect and approve midexit door plugs before the fuselage section is shipped to the planemaker, commercial aircraft chief Stan Deal said in a letter to employees Monday.

Boeing will also bring in an outside party to review its quality controls and suggest improvemen­ts, he said, adding another layer of scrutiny to its manufactur­ing process.

“Everything we do must conform to the requiremen­ts in our quality management system. Anything less is unacceptab­le,” Deal said. “Let each one of us take personal accountabi­lity and recommit ourselves to this important work.”

The planemaker was thrown into crisis Jan. 5 when a door-size fuselage panel tore off of a 737 Max 9 on Alaska Airlines Flight 1282 midflight. While the aircraft landed safely, the Federal Aviation Administra­tion has grounded most of the single-aisle variants of the jet as it investigat­es the accident.

The FAA has reacted quickly to increase oversight of Boeing, after being criticized for acting too slowly in response to two deadly 737 Max crashes nearly five years ago that cost 346 lives.

The agency last week initiated a probe of Boeing manufactur­ing, said it will increase monitoring of so-called in-service events on the Max 9, and plans to audit Boeing’s production line as well as those of its suppliers.

Many layers

Monday’s actions by Boeing are separate from the FAA’S investigat­ion and oversight plans, Deal said. “We will cooperate fully and transparen­tly with both as we work to restore trust with our regulator and our customers,” he said.

Spirit, a former Boeing unit, makes about 70% of the 737’s frame set at its base in Wichita, Kansas, including the plug on the Max 9 fuselage. The units are then shipped by rail to Boeing’s factory in Renton, Washington.

The National Transporta­tion Safety Board is investigat­ing the root cause of the accident. It has said that four locking bolts that secure the plug door to the frame are missing, and it’s not clear whether they were ever installed.

The door plug that ejected has been recovered and is undergoing inspection at an NTSB site.

Boeing is also inspecting more than 50 other points in Spirit’s manufactur­ing process and assessing the contractor’s build plans against engineerin­g specificat­ions, Deal said.

Spirit has been plagued by quality issues, including a glitch with misdrilled holes that caused a slowdown in 737 Max deliveries last year, and has been under financial stress. Boeing reworked some contracts with Spirit last year and provided additional financial aid to support its partner.

Airline scrutiny

The stakes are high for Boeing to repair the reputation of its cash-cow 737 Max. Airlines in China have delayed resuming 737 deliveries after missing and loose bolts were found in December, Bloomberg reported earlier.

The move to open Boeing’s factories to aircraft operators follows Alaska Air Group Inc.’s decision to expand quality checks on production of planes. The U.S. carrier, which relies on Boeing 737 aircraft, said over the weekend that it will hire more staff to enhance oversight of the planemaker’s production line.

Spirit will also open its factories to operators, Deal said, “and we will learn from our customers’ insights and findings.”

Newspapers in English