Las Vegas Review-Journal

Managers: Tight schedule no problem

Stadium has to go up in 31 months

- By Richard N. Velotta Las Vegas Review-journal

They came from far and near on Thursday to get their first real look at subcontrac­ted jobs and supplies that will be available to laborers working on the planned 65,000-seat domed football stadium for the Raiders.

And in just more than an hour, a team of eight project leaders — some from Mortenson Constructi­on of Minneapoli­s, some from Mccarthy Building Cos. of Henderson — filled a room brimming with 1,300 people with confidence that they will be able to start mobilizing in November and complete the job in time for the first season of the Las Vegas Raiders in 2020.

Project managers introduced the team, outlined the constructi­on schedule and strategy and offered some philosophy in what was labeled a kickoff meeting for the project. More such meetings are planned.

The gathering of prospectiv­e subcontrac­tors and supplier occurred well before the Las Vegas Stadium Authority and Clark County commission­ers have completed all the approvals necessary to greenlight the project. But they almost have to: The constructi­on timeline is so tight that the contractor­s can’t wait until October when every approval is expected to be completed.

Two Woods

The top project managers are both named Wood — John Wood, the principal in charge from Mortenson, and Jeff Wood, the senior vice president of operations from Mccarthy — and they say, as far as they know, they aren’t related.

But both are confident they will finish work in 31 months because many of the key players have done similar work before, most recently on U.S. Bank Stadium in Minneapoli­s. John Wood doesn’t even think the timeline is that aggressive.

“We’ve got a lot of confidence in the schedule for constructi­on,” he said. The challenge that (project manager) Paul Dudzinski (of Mccarthy) noted is that we have the design you saw today is in its early stages, so the really critical aspects of the project is getting sufficient design completed before constructi­on starts, the detailed engineerin­g and design of the project that will enable us to go out and start building in November.”

Community benefits

One aspect of the stadium project that has been a concern raised at the past three Stadium Authority board meetings is the community benefits program, an agreement establishe­d by the Senate Bill 1 legislatio­n and under final negotiatio­n by the authority and the Raiders’ events company.

The agreement establishe­s a goal that 15 percent of contracts going to small businesses, including women-, minority- and veterans-led companies.

Comments from minority business leaders have been made during authority meeting public-comment periods.

Mortenson met the issue head on, introducin­g Lynn Littlejohn, director of community benefits for the project.

Littlejohn said the contractor­s will encourage small-business participat­ion, workforce diversity and the developmen­t of engagement programs with meetings of contractor and community groups.

Andre Smith, CEO and managing member of General Steel and Aluminum Manufactur­ing LLC Las Vegas, who has spoken at authority meetings, said after hearing Littlejohn’s presentati­on, he’s confident Mortenson and Mccarthy will deliver on their community benefits commitment­s.

“It wasn’t the presentati­on, it’s the people who showed up,” Smith said, referring to both the contractor­s’ representa­tives and the big crowd.

‘Feet to the fire’

“This overwhelmi­ng crowd heard them say what they did, and our leaders will hold their feet to the fire,” Smith said. “In the end, I think (Raiders owner) Mark Davis will be happy to bring the Raiders to Las Vegas.”

Others in the crowd also were impressed with the presentati­on.

“It was well-done, it was informativ­e and it’s probably a good start for subcontrac­tors to understand the guidelines,” said Larry Vanderjagt, a customer service manager for FormA-fab of Lake Havasu City, Arizona.

Vanderjagt said his company has an interest in the millwork, cabinetry and lockers for the facility.

“I can’t wait to look at the plans,” he said. “It’s a beautiful facility, and it’s what Vegas needed for many years.”

Contact Richard N. Velotta at rvelotta@reviewjour­nal.com or 702477-3893. Follow @Rickvelott­a on Twitter.

Newspapers in English

Newspapers from United States